On the DLD projects register
- Projects
- 5
- Live
- 1
- Completed
- 4
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 5 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 12 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- CHORISIA 1 VILLASRegistered status: Finished
Wadi Al Safa 3 · 60 land plots
- Started
- 11 Oct 2021
- Current planned completion
- 30 Mar 2023
- Completed
- 30 Mar 2023
- DLD project 2218Registered status: Pending5% complete
Wadi Al Safa 3
- Started
- 15 Nov 2020
- Current planned completion
- Not published
- Seventh Heaven - AshjarRegistered status: Finished
Wadi Al Safa 3 · 302 units, 13 buildings, 3 land plots
- Started
- 01 Dec 2014
- Current planned completion
- 30 Dec 2022
- Completed
- 30 Dec 2022
118 unit and villa sales in the year to Sep 2026
- SEVENTH HEAVENRegistered status: Finished
Wadi Al Safa 3 · 223 units, 1 building
- Started
- 01 Jun 2014
- Current planned completion
- 08 Sep 2020
- Completed
- 08 Sep 2020
14 unit and villa sales in the year to Sep 2026
- DLD project 1074Registered status: Finished
Wadi Al Safa 3
- Started
- 22 Apr 2007
- Current planned completion
- 27 Feb 2012
- Completed
- 28 Oct 2010
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 12 Nov 2026.