Dubai Land Department records

Developer

AG PROPERTIES L.L.C

DLD developer number 1398Registered with DLD on 14 Dec 2021

On the DLD projects register

Projects
4
Live
4
Completed
0
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 4 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. AG 9INE
    Registered status: Active
    38.4% complete

    Wadi Al Safa 5 · 260 units, 1 building

    Started
    31 Jan 2024
    Current planned completion
    Not published

    12 unit and villa sales in the year to Sep 2026

  2. AG CENTRAL
    Registered status: Active
    58.7% complete

    Wadi Al Safa 5 · 96 units, 1 building

    Started
    31 Oct 2023
    Current planned completion
    31 Oct 2026

    3 unit and villa sales in the year to Sep 2026

  3. AG 7EVEN
    Registered status: Active
    93.7% complete

    Wadi Al Safa 5 · 234 units, 1 building

    Started
    31 Mar 2023
    Current planned completion
    31 Mar 2027

    17 unit and villa sales in the year to Sep 2026

  4. AG SQUARE
    Registered status: Active
    68.8% complete

    Wadi Al Safa 5 · 372 units, 1 building

    Started
    30 Sep 2022
    Current planned completion
    30 Sep 2026

    40 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.