Developer

AL MANAL DEVELOPMENT FZCO

DLD developer number 4Registered with DLD on 29 Jul 2007

On the DLD projects register

Projects
7
Live
0
Completed
7
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 7 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. LA VISITA 01
    Registered status: Finished

    Nadd Hessa · 128 units, 1 building

    Started
    17 May 2008
    Current planned completion
    13 Mar 2014
    Completed
    13 Mar 2014

    10 unit and villa sales in the year to Sep 2026

  2. LA VISTA 03
    Registered status: Finished

    Nadd Hessa · 128 units, 1 building

    Started
    17 May 2008
    Current planned completion
    16 Apr 2015
    Completed
    16 Apr 2015

    18 unit and villa sales in the year to Sep 2026

  3. LA VISTA 04
    Registered status: Finished

    Nadd Hessa · 128 units, 1 building

    Started
    17 May 2008
    Current planned completion
    05 Sep 2017
    Completed
    31 Jan 2016
  4. LA VISITA 02
    Registered status: Finished

    Nadd Hessa · 128 units, 1 building

    Started
    17 May 2008
    Current planned completion
    30 Dec 2010
    Completed
    23 Jun 2013

    12 unit and villa sales in the year to Sep 2026

  5. LA VISTA 05
    Registered status: Finished

    Nadd Hessa · 133 units, 1 building

    Started
    17 May 2008
    Current planned completion
    30 Apr 2018
    Completed
    30 Jun 2016
  6. LA VISTA 06
    Registered status: Finished

    Nadd Hessa · 96 units, 1 building

    Started
    17 May 2008
    Current planned completion
    17 Sep 2013
    Completed
    17 Sep 2013
  7. LAKESIDE RESIDENCE
    Registered status: Finished

    Al Thanyah Fifth · 358 units, 1 building

    Started
    17 Aug 2006
    Current planned completion
    17 Dec 2012
    Completed
    17 Dec 2012

    24 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.