Developer
AL MAZAYA REAL ESTATE FZ-LLC
DLD developer number 903Registered with DLD on 22 Jan 2012
On the DLD projects register
- Projects
- 33
- Live
- 0
- Completed
- 33
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 33 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 12 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- QPOINT LIWAN-PLOT R094Registered status: Finished
Wadi Al Safa 2 · 55 units, 1 building
- Started
- 01 Jul 2009
- Current planned completion
- 11 Nov 2013
- Completed
- 11 Nov 2013
7 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN- R093Registered status: Finished
Wadi Al Safa 2 · 65 units, 1 building
- Started
- 01 Jul 2009
- Current planned completion
- 23 Jul 2014
- Completed
- 23 Jul 2014
9 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R092Registered status: Finished
Wadi Al Safa 2 · 80 units, 1 building
- Started
- 01 Jul 2009
- Current planned completion
- 11 Nov 2013
- Completed
- 11 Nov 2013
6 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R095Registered status: Finished
Wadi Al Safa 2 · 55 units, 1 building
- Started
- 01 Jul 2009
- Current planned completion
- 09 Oct 2014
- Completed
- 09 Oct 2014
3 unit and villa sales in the year to Sep 2026
- DLD project 1183Registered status: Finished
Wadi Al Safa 2 · 230 units, 2 buildings
- Started
- 01 Jun 2009
- Current planned completion
- 01 Jun 2014
- Completed
- 01 Jun 2014
- QPOINT LIWAN-PLOT R099Registered status: Finished
Wadi Al Safa 2 · 55 units, 1 building
- Started
- 01 Jun 2009
- Current planned completion
- 11 Nov 2014
- Completed
- 11 Nov 2014
5 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R100Registered status: Finished
Wadi Al Safa 2 · 40 units, 1 building
- Started
- 01 Jun 2009
- Current planned completion
- 24 Jun 2014
- Completed
- 24 Jun 2014
- QPOINT LIWAN-R019Registered status: Finished
Wadi Al Safa 2 · 60 units, 1 building
- Started
- 01 May 2009
- Current planned completion
- 14 Jan 2014
- Completed
- 14 Jan 2014
8 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R050Registered status: Finished
Wadi Al Safa 2 · 73 units, 1 building
- Started
- 01 May 2009
- Current planned completion
- 30 Jan 2014
- Completed
- 30 Jan 2014
- QPOINT LIWAN-PLOT R055Registered status: Finished
Wadi Al Safa 2 · 82 units, 1 building
- Started
- 01 May 2009
- Current planned completion
- 01 Oct 2014
- Completed
- 01 Oct 2014
6 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R097Registered status: Finished
Wadi Al Safa 2 · 55 units, 1 building
- Started
- 01 May 2009
- Current planned completion
- 03 Jun 2014
- Completed
- 03 Jun 2014
6 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R098Registered status: Finished
Wadi Al Safa 2 · 55 units, 1 building
- Started
- 01 May 2009
- Current planned completion
- 05 May 2014
- Completed
- 05 May 2014
9 unit and villa sales in the year to Sep 2026
21 more projects
- QPOINT LIWAN-PLOT R020Registered status: Finished
Wadi Al Safa 2 · 81 units, 1 building
- Started
- 01 May 2009
- Current planned completion
- 24 Sep 2014
- Completed
- 24 Sep 2014
4 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R051Registered status: Finished
Wadi Al Safa 2 · 58 units, 1 building
- Started
- 25 Mar 2009
- Current planned completion
- 17 Jan 2017
- Completed
- 12 Nov 2014
8 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R046Registered status: Finished
Wadi Al Safa 2 · 57 units, 1 building
- Started
- 22 Mar 2009
- Current planned completion
- 17 Jan 2017
- Completed
- 25 Dec 2016
3 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R015Registered status: Finished
Wadi Al Safa 2 · 90 units, 1 building
- Started
- 19 Mar 2009
- Current planned completion
- 02 Feb 2017
- Completed
- 02 Feb 2017
5 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R073Registered status: Finished
Wadi Al Safa 2 · 61 units, 1 building
- Started
- 19 Mar 2009
- Current planned completion
- 06 Aug 2015
- Completed
- 06 Aug 2015
- QPOINT LIWAN-PLOT R081Registered status: Finished
Wadi Al Safa 2 · 95 units, 1 building
- Started
- 19 Mar 2009
- Current planned completion
- 02 Apr 2020
- Completed
- 15 Dec 2014
- QPOINT LIWAN-PLOT R082Registered status: Finished
Wadi Al Safa 2 · 95 units, 1 building
- Started
- 19 Mar 2009
- Current planned completion
- 02 Oct 2018
- Completed
- 15 Jul 2015
- QPOINT LIWAN-PLOT R022Registered status: Finished
Wadi Al Safa 2 · 65 units, 1 building
- Started
- 19 Mar 2009
- Current planned completion
- 24 Oct 2016
- Completed
- 28 Feb 2012
2 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R048Registered status: Finished
Wadi Al Safa 2 · 50 units, 1 building
- Started
- 24 Feb 2009
- Current planned completion
- 31 Mar 2014
- Completed
- 24 Feb 2014
5 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R047Registered status: Finished
Wadi Al Safa 2 · 96 units, 1 building
- Started
- 24 Feb 2009
- Current planned completion
- 21 Apr 2014
- Completed
- 21 Apr 2014
5 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R004Registered status: Finished
Wadi Al Safa 2 · 220 units, 1 building
- Started
- 18 Dec 2008
- Current planned completion
- 17 Aug 2014
- Completed
- 17 Aug 2014
11 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R005Registered status: Finished
Wadi Al Safa 2 · 217 units, 1 building
- Started
- 18 Dec 2008
- Current planned completion
- 26 May 2014
- Completed
- 26 May 2014
23 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN - PLOT R002Registered status: Finished
Wadi Al Safa 2 · 78 units, 1 building
- Started
- 27 Oct 2008
- Current planned completion
- 18 Feb 2014
- Completed
- 18 Dec 2014
11 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN - PLOT R003Registered status: Finished
Wadi Al Safa 2 · 91 units, 1 building
- Started
- 28 Aug 2008
- Current planned completion
- 26 Mar 2017
- Completed
- 01 Apr 2014
9 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R052Registered status: Finished
Wadi Al Safa 2 · 67 units, 1 building
- Started
- 04 Aug 2008
- Current planned completion
- 28 Sep 2016
- Completed
- 28 Sep 2016
2 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R053Registered status: Finished
Wadi Al Safa 2 · 67 units, 1 building
- Started
- 04 Aug 2008
- Current planned completion
- 27 Jun 2016
- Completed
- 15 Jul 2015
2 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R071Registered status: Finished
Wadi Al Safa 2 · 61 units, 1 building
- Started
- 24 Jun 2008
- Current planned completion
- 06 Oct 2013
- Completed
- 06 Oct 2013
3 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R072Registered status: Finished
Wadi Al Safa 2 · 61 units, 1 building
- Started
- 24 Jun 2008
- Current planned completion
- 03 Oct 2013
- Completed
- 03 Oct 2013
11 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R068Registered status: Finished
Wadi Al Safa 2 · 62 units, 2 buildings
- Started
- 28 May 2008
- Current planned completion
- 26 Sep 2013
- Completed
- 26 Sep 2013
6 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R069Registered status: Finished
Wadi Al Safa 2 · 61 units, 1 building
- Started
- 28 May 2008
- Current planned completion
- 09 Sep 2013
- Completed
- 09 Sep 2013
6 unit and villa sales in the year to Sep 2026
- QPOINT LIWAN-PLOT R070Registered status: Finished
Wadi Al Safa 2 · 61 units, 1 building
- Started
- 28 May 2008
- Current planned completion
- 15 Mar 2013
- Completed
- 29 Aug 2013
4 unit and villa sales in the year to Sep 2026