Developer
AL QUDRA ESTATES L.L.C
DLD developer number 1270Registered with DLD on 03 Mar 2019
On the DLD projects register
- Projects
- 3
- Live
- 1
- Completed
- 2
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 3 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Nad Al Sheba Gardens Phase 3Registered status: Active97% complete
Nad Al Shiba First · 235 villas, 117 land plots
- Started
- 09 Jan 2023
- Current planned completion
- 19 Apr 2026
20 unit and villa sales in the year to Sep 2026
- Nad Al Sheba Gardens Phase 2Registered status: Finished
Nad Al Shiba First · 212 villas, 202 land plots
- Started
- 10 Jul 2022
- Current planned completion
- 01 Dec 2024
- Completed
- 17 Dec 2025
4 unit and villa sales in the year to Sep 2026
- CherrywoodsRegistered status: Finished
Al Yelayiss 1 · 378 villas, 102 land plots
- Started
- 27 Jun 2019
- Current planned completion
- 31 May 2022
- Completed
- 27 Jun 2021
26 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.