Dubai Land Department records

Developer

ALTA REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 1300Registered with DLD on 31 Dec 2020

On the DLD projects register

Projects
3
Live
2
Completed
1
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 3 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. MAISON MARGIELA RESIDENCES
    Registered status: Active
    6.4% complete

    Palm Jumeirah · 25 units, 1 building

    Started
    28 Mar 2025
    Current planned completion
    27 Mar 2028
  2. MR.C RESIDENCES DOWNTOWN
    Registered status: Active
    73.2% complete

    Al Wasl · 169 units, 1 building

    Started
    11 Sep 2021
    Current planned completion
    27 Jan 2027

    33 unit and villa sales in the year to Sep 2026

  3. MR. C RESIDENCES JUMEIRAH
    Registered status: Finished

    Jumeirah Second · 27 units, 4 buildings

    Started
    18 Jun 2021
    Current planned completion
    21 Jan 2024
    Completed
    21 Jan 2024

    2 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.