Dubai Land Department records

Developer

ARTAR REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 1082Registered with DLD on 02 Jun 2015

On the DLD projects register

Projects
2
Live
1
Completed
1
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 2 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4525
    Registered status: Pending
    65% complete

    Business Bay

    Started
    31 Jul 2027
    Current planned completion
    31 Jul 2028
  2. MADA RESIDENCES TOWER
    Registered status: Finished

    Burj Khalifa · 193 units, 1 building

    Started
    01 Sep 2015
    Current planned completion
    30 Jun 2018
    Completed
    30 Jun 2018

    18 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.