Developer
AVELON REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 1826Registered with DLD on 08 Jan 2024
On the DLD projects register
- Projects
- 2
- Live
- 1
- Completed
- 1
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 2 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- TrevinoRegistered status: Not started0% complete
Al Barsha South Fourth · 109 units, 1 building
- Started
- 01 Aug 2025
- Current planned completion
- 30 Jun 2027
37 unit and villa sales in the year to Sep 2026
- Avelon BoulevardRegistered status: Finished
Al Barshaa South Third · 135 units, 1 building
- Started
- 15 Apr 2024
- Current planned completion
- 30 Sep 2025
- Completed
- 25 Dec 2025
25 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.