Dubai Land Department records

Developer

B N H REAL ESTATE DEVELOPER

DLD developer number 1219Registered with DLD on 15 Oct 2017

On the DLD projects register

Projects
7
Live
2
Completed
5
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 7 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. EQUITI TOWER
    Registered status: Active
    70.2% complete

    Warsan Fourth · 88 units, 1 building

    Started
    12 Jun 2024
    Current planned completion
    30 Aug 2025

    79 unit and villa sales in the year to Sep 2026

  2. EQUITI GARDEN
    Registered status: Active
    87% complete

    Jabal Ali First · 133 units, 1 building

    Started
    14 Dec 2023
    Current planned completion
    13 Dec 2025

    31 unit and villa sales in the year to Sep 2026

  3. EQUITI HOME
    Registered status: Finished

    Jabal Ali First · 302 units, 2 buildings

    Started
    21 Jan 2023
    Current planned completion
    Not published
    Completed
    08 Jan 2026

    44 unit and villa sales in the year to Sep 2026

  4. EQUITI GATES
    Registered status: Finished

    Jabal Ali Industrial Second · 284 units, 1 building

    Started
    06 Oct 2022
    Current planned completion
    Not published
    Completed
    21 Oct 2025

    19 unit and villa sales in the year to Sep 2026

  5. EQUITI ARCADE
    Registered status: Finished

    Jabal Ali First · 83 units, 1 building

    Started
    04 Aug 2022
    Current planned completion
    31 Dec 2023
    Completed
    31 Dec 2023

    14 unit and villa sales in the year to Sep 2026

  6. EQUITI RESIDENCE
    Registered status: Finished

    Jabal Ali First · 90 units, 1 building

    Started
    02 Sep 2021
    Current planned completion
    31 Dec 2022
    Completed
    31 Dec 2022

    9 unit and villa sales in the year to Sep 2026

  7. EQUITI APARTMENTS
    Registered status: Finished

    Warsan Fourth · 135 units, 1 building

    Started
    10 Apr 2021
    Current planned completion
    31 Dec 2022
    Completed
    31 Dec 2022

    13 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.