Developer
BC RESIDENCES L.L.C
DLD developer number 1580Registered with DLD on 15 Mar 2023
On the DLD projects register
- Projects
- 1
- Live
- 1
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 1 project.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Baccarat Hotel and Residences, DubaiRegistered status: Active21.2% complete
Burj Khalifa · 98 units, 2 buildings
- Started
- 20 Mar 2023
- Current planned completion
- 29 Dec 2026
31 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.