Dubai Land Department records

Developer

D H G PROPERTY DEVELOPMENT L.L.C

DLD developer number 1619Registered with DLD on 15 May 2023

On the DLD projects register

Projects
3
Live
2
Completed
1
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
2

No planned completion date has moved since we started checking in Oct 2026, across 3 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Helvetia Marine
    Registered status: Not started
    0% complete

    Palm Deira · 63 units, 1 building

    Started
    23 Jan 2026
    Current planned completion
    15 Mar 2028

    10 unit and villa sales in the year to Sep 2026

  2. Helvetia Verde
    Registered status: Active
    0.6% complete

    Bukadra · 109 units, 1 building

    Started
    01 Jan 2026
    Current planned completion
    30 Nov 2027

    8 unit and villa sales in the year to Sep 2026

  3. HELVETIA RESIDENCES
    Registered status: Finished

    Al Barsha South Fourth · 432 units, 1 building

    Started
    18 Dec 2023
    Current planned completion
    Not published
    Completed
    30 Sep 2026

    67 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.