Developer

DAMAC STAR PROPERTIES (L L C)

DLD developer number 907Registered with DLD on 09 Feb 2011

On the DLD projects register

Projects
12
Live
0
Completed
12
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 12 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. AVANTI TOWER
    Registered status: Finished

    Business Bay · 161 units, 1 building

    Started
    01 Aug 2014
    Current planned completion
    16 Dec 2018
    Completed
    16 Dec 2018

    11 unit and villa sales in the year to Sep 2026

  2. DLD project 418
    Registered status: Finished

    Business Bay · 222 units, 1 building

    Started
    01 Jun 2010
    Current planned completion
    12 Dec 2013
    Completed
    12 Dec 2013
  3. THE VOGUE
    Registered status: Finished

    Business Bay · 191 units, 1 building

    Started
    01 May 2010
    Current planned completion
    05 Jun 2014
    Completed
    05 Jun 2014

    20 unit and villa sales in the year to Sep 2026

  4. THE COSMOPOLITAN
    Registered status: Finished

    Business Bay · 368 units, 1 building

    Started
    01 Apr 2010
    Current planned completion
    13 Mar 2014
    Completed
    16 Mar 2014

    27 unit and villa sales in the year to Sep 2026

  5. THE RESIDENCE AT BUSINESS CENTRAL
    Registered status: Finished

    Business Bay · 228 units, 2 buildings

    Started
    01 Apr 2010
    Current planned completion
    05 Feb 2013
    Completed
    05 Feb 2013

    24 unit and villa sales in the year to Sep 2026

  6. THE SIGNATURE
    Registered status: Finished

    Burj Khalifa · 356 units, 1 building

    Started
    15 Mar 2010
    Current planned completion
    21 May 2013
    Completed
    21 May 2013

    34 unit and villa sales in the year to Sep 2026

  7. PARK CENTRAL
    Registered status: Finished

    Business Bay · 146 units, 2 buildings

    Started
    01 Mar 2010
    Current planned completion
    20 Nov 2013
    Completed
    20 Nov 2013

    20 unit and villa sales in the year to Sep 2026

  8. DLD project 446
    Registered status: Finished

    Business Bay

    Started
    01 Mar 2010
    Current planned completion
    09 Mar 2014
    Completed
    09 Mar 2014
  9. CAPITAL BAY A
    Registered status: Finished

    Business Bay · 177 units

    Started
    01 Mar 2010
    Current planned completion
    30 Mar 2014
    Completed
    13 Apr 2014

    17 unit and villa sales in the year to Sep 2026

  10. EXECUTIVE BAY B
    Registered status: Finished

    Business Bay · 297 units, 4 buildings

    Started
    01 Mar 2010
    Current planned completion
    09 Mar 2014
    Completed
    09 Mar 2014

    22 unit and villa sales in the year to Sep 2026

  11. CAPITAL BAY B
    Registered status: Finished

    Business Bay · 186 units, 3 buildings

    Started
    01 Mar 2010
    Current planned completion
    13 Apr 2014
    Completed
    13 Apr 2014

    31 unit and villa sales in the year to Sep 2026

  12. DAMAC TOWERS BY PARAMOUNT
    Registered status: Finished

    Business Bay · 2,041 units, 5 buildings

    Started
    27 Mar 2008
    Current planned completion
    23 Oct 2018
    Completed
    23 Oct 2018

    150 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.