Developer
DEYAAR DEVELOPMENT (P.J.S.C)
DLD developer number 15Registered with DLD on 21 Aug 2007
On the DLD projects register
- Projects
- 38
- Live
- 10
- Completed
- 28
- Cancelled
- 0
- Planned completion in the next 12 months
- 2
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 38 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- ALDER AT PARK FIVERegistered status: Active6.1% complete
Me'Aisem First · 75 units, 1 building
- Started
- 01 Mar 2026
- Current planned completion
- 31 Dec 2027
66 unit and villa sales in the year to Sep 2026
- Downtown ResidencesRegistered status: Active1.3% complete
Business Bay · 524 units, 1 building
- Started
- 01 Dec 2025
- Current planned completion
- 30 Dec 2030
361 unit and villa sales in the year to Sep 2026
- IVY AT PARK FIVERegistered status: Active6.3% complete
Me'Aisem First · 210 units, 1 building
- Started
- 01 Nov 2025
- Current planned completion
- 31 Dec 2027
178 unit and villa sales in the year to Sep 2026
- NEEM AT PARK FIVERegistered status: Active15.2% complete
Me'Aisem First · 145 units, 1 building
- Started
- 01 Jul 2025
- Current planned completion
- 01 Dec 2027
109 unit and villa sales in the year to Sep 2026
- ELM AT PARK FIVERegistered status: Active16.2% complete
Me'Aisem First · 532 units, 2 buildings
- Started
- 01 Apr 2025
- Current planned completion
- 01 Jun 2027
137 unit and villa sales in the year to Sep 2026
- EMBER AT PARK FIVERegistered status: Active18.2% complete
Me'Aisem First · 205 units, 1 building
- Started
- 01 Apr 2025
- Current planned completion
- 01 Jun 2027
117 unit and villa sales in the year to Sep 2026
- ELEVE BY DEYAARRegistered status: Active20% complete
Jabal Ali Industrial Second · 818 units, 1 building
- Started
- 31 Oct 2024
- Current planned completion
- Not published
146 unit and villa sales in the year to Sep 2026
- JANNATRegistered status: Finished
Me'Aisem First · 362 units, 1 building
- Started
- 01 Dec 2023
- Current planned completion
- Not published
- Completed
- 04 Jun 2026
55 unit and villa sales in the year to Sep 2026
- ROSALIA RESIDENCESRegistered status: Active82% complete
Jabal Ali First · 118 units, 1 building
- Started
- 30 Sep 2023
- Current planned completion
- Not published
5 unit and villa sales in the year to Sep 2026
- MAR CASARegistered status: Active56.5% complete
Madinat Dubai Almelaheyah · 585 units, 1 building
- Started
- 01 Sep 2023
- Current planned completion
- 31 Oct 2026
33 unit and villa sales in the year to Sep 2026
- AMALIA RESIDENCESRegistered status: Finished
Jabal Ali First · 98 units, 1 building
- Started
- 31 Mar 2023
- Current planned completion
- 31 Jan 2025
- Completed
- 17 Nov 2025
24 unit and villa sales in the year to Sep 2026
- TALIA RESIDENCESRegistered status: Finished
Jabal Ali First · 160 units, 1 building
- Started
- 31 Mar 2023
- Current planned completion
- 30 Apr 2025
- Completed
- 01 Jun 2026
21 unit and villa sales in the year to Sep 2026
26 more projects
- RegaliaRegistered status: Finished
Business Bay · 913 units, 1 building
- Started
- 01 Aug 2021
- Current planned completion
- 31 Dec 2024
- Completed
- 29 Apr 2026
97 unit and villa sales in the year to Sep 2026
- MIDTOWN - NOORRegistered status: Finished
Me'Aisem First · 606 units, 5 buildings
- Started
- 29 Feb 2020
- Current planned completion
- 28 Feb 2023
- Completed
- 28 Feb 2023
51 unit and villa sales in the year to Sep 2026
- MIDTOWN - MESKRegistered status: Finished
Me'Aisem First · 282 units, 2 buildings
- Started
- 29 Feb 2020
- Current planned completion
- 31 Aug 2022
- Completed
- 31 Aug 2022
37 unit and villa sales in the year to Sep 2026
- MIDTOWN - DANIARegistered status: Finished
Me'Aisem First · 591 units, 4 buildings
- Started
- 01 Nov 2016
- Current planned completion
- 01 Mar 2020
- Completed
- 01 Mar 2020
40 unit and villa sales in the year to Sep 2026
- MIDTOWN - AFNANRegistered status: Finished
Me'Aisem First · 677 units, 5 buildings
- Started
- 01 May 2016
- Current planned completion
- 24 Oct 2019
- Completed
- 24 Oct 2019
62 unit and villa sales in the year to Sep 2026
- MONTROSERegistered status: Finished
Al Barshaa South Second · 302 units, 2 buildings
- Started
- 01 Jul 2014
- Current planned completion
- 08 Apr 2018
- Completed
- 08 Apr 2018
20 unit and villa sales in the year to Sep 2026
- THE ATRIARegistered status: Finished
Business Bay · 577 units, 2 buildings
- Started
- 20 Feb 2014
- Current planned completion
- 30 Apr 2018
- Completed
- 30 Apr 2018
19 unit and villa sales in the year to Sep 2026
- RUBY RESIDENCERegistered status: Finished
Nadd Hessa · 138 units, 1 building
- Started
- 28 Aug 2008
- Current planned completion
- 09 Feb 2010
- Completed
- 09 Feb 2010
9 unit and villa sales in the year to Sep 2026
- OXFORD TOWERRegistered status: Finished
Business Bay · 105 units, 1 building
- Started
- 13 Jul 2008
- Current planned completion
- 30 Dec 2012
- Completed
- 30 Dec 2012
6 unit and villa sales in the year to Sep 2026
- FAIR VIEW RESIDENCYRegistered status: Finished
Business Bay · 177 units, 1 building
- Started
- 01 Jul 2008
- Current planned completion
- 26 Feb 2014
- Completed
- 26 Feb 2014
13 unit and villa sales in the year to Sep 2026
- DLD project 41Registered status: Finished
Business Bay · 176 units, 1 building
- Started
- 12 Feb 2008
- Current planned completion
- 09 Feb 2012
- Completed
- 09 Feb 2012
- CORAL RESIDENCERegistered status: Finished
Nadd Hessa · 145 units, 1 building
- Started
- 28 Jan 2008
- Current planned completion
- 09 Feb 2010
- Completed
- 09 Feb 2010
13 unit and villa sales in the year to Sep 2026
- SAPPHIRE RESIDENCERegistered status: Finished
Nadd Hessa · 90 units, 1 building
- Started
- 28 Jan 2008
- Current planned completion
- 04 Feb 2010
- Completed
- 04 Feb 2010
11 unit and villa sales in the year to Sep 2026
- HAMILTON RESIDENCYRegistered status: Finished
Business Bay · 183 units, 1 building
- Started
- 04 Dec 2007
- Current planned completion
- 20 May 2010
- Completed
- 20 May 2010
15 unit and villa sales in the year to Sep 2026
- MAYFAIR RESIDENCYRegistered status: Finished
Business Bay · 217 units, 1 building
- Started
- 18 Nov 2007
- Current planned completion
- 12 Jan 2011
- Completed
- 12 Jan 2011
21 unit and villa sales in the year to Sep 2026
- OAKWOOD RESIDENCYRegistered status: Finished
Me'Aisem First · 348 units, 1 building
- Started
- 18 Oct 2007
- Current planned completion
- 01 Jul 2012
- Completed
- 01 Jul 2012
23 unit and villa sales in the year to Sep 2026
- CLAYTON RESIDENCYRegistered status: Finished
Business Bay · 173 units, 1 building
- Started
- 01 Oct 2007
- Current planned completion
- 13 Mar 2011
- Completed
- 13 Mar 2011
10 unit and villa sales in the year to Sep 2026
- JADE RESIDENCERegistered status: Finished
Nadd Hessa · 97 units, 1 building
- Started
- 28 Aug 2007
- Current planned completion
- 06 Oct 2009
- Completed
- 06 Oct 2009
10 unit and villa sales in the year to Sep 2026
- MAYFAIR TOWERRegistered status: Finished
Business Bay · 224 units, 1 building
- Started
- 16 Aug 2007
- Current planned completion
- 13 Mar 2011
- Completed
- 13 Mar 2011
9 unit and villa sales in the year to Sep 2026
- BURLINGTON TOWERRegistered status: Finished
Business Bay · 501 units, 1 building
- Started
- 30 Apr 2007
- Current planned completion
- 30 Dec 2012
- Completed
- 19 Sep 2013
44 unit and villa sales in the year to Sep 2026
- THE MERTOPOLISRegistered status: Finished
Business Bay · 332 units, 1 building
- Started
- 06 Sep 2006
- Current planned completion
- 27 Mar 2011
- Completed
- 27 Mar 2011
18 unit and villa sales in the year to Sep 2026
- CITADEL TOWERRegistered status: Finished
Business Bay · 419 units, 1 building
- Started
- 01 Jul 2006
- Current planned completion
- 10 Jan 2010
- Completed
- 10 Jan 2010
19 unit and villa sales in the year to Sep 2026
- MADISON RESIDENCYRegistered status: Finished
Al Thanyah First · 311 units, 1 building
- Started
- 01 May 2006
- Current planned completion
- 28 Apr 2009
- Completed
- 28 Apr 2009
20 unit and villa sales in the year to Sep 2026
- AL SEEF IIRegistered status: Finished
Al Thanyah Fifth · 229 units, 1 building
- Started
- 11 Jun 2005
- Current planned completion
- 06 Nov 2008
- Completed
- 06 Nov 2008
9 unit and villa sales in the year to Sep 2026
- ALSEEF IRegistered status: Finished
Marsa Dubai · 166 units, 1 building
- Started
- 17 May 2003
- Current planned completion
- 13 Apr 2005
- Completed
- 13 Apr 2005
5 unit and villa sales in the year to Sep 2026
- DLD project 1478Registered status: Finished
Al Barshaa South Second
- Started
- Not published
- Current planned completion
- Not published
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.