Developer
DUBAI ISLANDS L.L.C
DLD developer number 105Registered with DLD on 01 Jul 2007
On the DLD projects register
- Projects
- 6
- Live
- 6
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 6 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Bay EstateRegistered status: Not started0% complete
Palm Deira · 357 villas, 356 land plots
- Started
- 30 Oct 2026
- Current planned completion
- 15 Aug 2030
- Bay Grove Residences D - Dubai IslandsRegistered status: Active3.7% complete
Palm Deira · 257 units, 4 buildings
- Started
- 17 Aug 2025
- Current planned completion
- 15 Sep 2028
185 unit and villa sales in the year to Sep 2026
- Bay Grove Residences B - Dubai IslandsRegistered status: Active7.6% complete
Palm Deira · 241 units, 3 buildings
- Started
- 17 Jun 2025
- Current planned completion
- 21 Sep 2028
1 unit or villa sale in the year to Sep 2026
- Bay Grove Residences C - Dubai IslandsRegistered status: Active7.3% complete
Palm Deira · 360 units, 4 buildings
- Started
- 15 Feb 2025
- Current planned completion
- 10 Apr 2028
8 unit and villa sales in the year to Sep 2026
- Bay Grove Residences, Dubai IslandsRegistered status: Active12.3% complete
Palm Deira · 296 units, 4 buildings
- Started
- 22 Dec 2024
- Current planned completion
- 15 Mar 2028
9 unit and villa sales in the year to Sep 2026
- Bay Villas - Dubai IslandsRegistered status: Active22.8% complete
Palm Deira · 635 land plots
- Started
- 26 Jul 2024
- Current planned completion
- 02 May 2027
Source: DLD projects register, read 11 Nov 2026.