DUBAI PENINSULA L.L.C

DLD developer number 1499Registered with DLD on 10 Oct 2022

On the DLD projects register

Projects
3
Live
3
Completed
0
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 3 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 3398
    Registered status: Pending
    0% complete

    Jumeirah Second

    Started
    01 Oct 2025
    Current planned completion
    30 Nov 2028
  2. Peninsula Dubai Residences - Tower 1
    Registered status: Active
    5.6% complete

    Jumeirah Second · 75 units, 1 building

    Started
    03 Mar 2025
    Current planned completion
    08 Jan 2029

    15 unit and villa sales in the year to Sep 2026

  3. Peninsula Dubai Residences - Tower 2
    Registered status: Active
    6% complete

    Jumeirah Second · 102 units, 1 building

    Started
    03 Mar 2025
    Current planned completion
    08 Jan 2029

    33 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.