Developer
DUBAI WHARF L.L.C
DLD developer number 1031Registered with DLD on 17 Sep 2014
On the DLD projects register
- Projects
- 3
- Live
- 0
- Completed
- 3
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 3 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Dubai Wharf - Tower 2Registered status: Finished
Al Jadaf · 254 units, 1 building
- Started
- 30 Oct 2014
- Current planned completion
- 15 Feb 2017
- Completed
- 15 Feb 2017
15 unit and villa sales in the year to Sep 2026
- Dubai Wharf - Tower 1Registered status: Finished
Al Jadaf · 128 units, 1 building
- Started
- 30 Oct 2014
- Current planned completion
- 30 Mar 2017
- Completed
- 30 Mar 2017
- DUBAI WHARFRegistered status: Finished
Al Jadaf · 124 units, 1 building
- Started
- 01 Oct 2014
- Current planned completion
- 21 Dec 2016
- Completed
- 31 Dec 2016
4 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.