Dubai Land Department records

Developer

ELLINGTON PROPERTIES DEVELOPMENT L.L.C

DLD developer number 1117Registered with DLD on 13 Jan 2016

On the DLD projects register

Projects
34
Live
18
Completed
16
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
1

No planned completion date has moved since we started checking in Oct 2026, across 34 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. WINDSOR HOUSE II
    Registered status: Active
    0.6% complete

    Madinat Al Mataar · 424 units, 3 buildings

    Started
    12 Feb 2026
    Current planned completion
    31 Jul 2029

    398 unit and villa sales in the year to Sep 2026

  2. EATON SQUARE
    Registered status: Active
    5.4% complete

    Bukadra · 24 units, 1 building

    Started
    01 Dec 2025
    Current planned completion
    30 Jun 2028

    17 unit and villa sales in the year to Sep 2026

  3. ELLINGTON SANDS I
    Registered status: Not started
    0.4% complete

    Palm Deira · 471 units, 2 buildings

    Started
    10 Oct 2025
    Current planned completion
    31 Dec 2028

    429 unit and villa sales in the year to Sep 2026

  4. ELLINGTON SANDS II
    Registered status: Not started
    0.4% complete

    Palm Deira · 460 units, 2 buildings

    Started
    10 Oct 2025
    Current planned completion
    31 Dec 2028

    418 unit and villa sales in the year to Sep 2026

  5. THE HIGHGROVE
    Registered status: Active
    7% complete

    Bukadra · 296 units, 1 building

    Started
    01 Sep 2025
    Current planned completion
    31 Dec 2028

    105 unit and villa sales in the year to Sep 2026

  6. BELMORE RESIDENCES
    Registered status: Active
    6.5% complete

    Bukadra · 214 units, 1 building

    Started
    07 Aug 2025
    Current planned completion
    31 Dec 2027

    131 unit and villa sales in the year to Sep 2026

  7. THE HILLGATE
    Registered status: Active
    3.1% complete

    Nadd Hessa · 356 units, 2 buildings

    Started
    03 Mar 2025
    Current planned completion
    30 Jun 2028

    215 unit and villa sales in the year to Sep 2026

  8. THE WATERCREST BY ELLINGTON
    Registered status: Active
    2.2% complete

    Wadi Al Safa 3 · 84 villas

    Started
    31 Jan 2025
    Current planned completion
    31 Mar 2028

    28 unit and villa sales in the year to Sep 2026

  9. ROSEMONT RESIDENCES
    Registered status: Active
    42.9% complete

    Al Barsha South Fifth · 49 units, 1 building

    Started
    14 Mar 2024
    Current planned completion
    Not published

    3 unit and villa sales in the year to Sep 2026

  10. THE BEACHFRONT VILLAS BY ELLINGTON
    Registered status: Active
    47.4% complete

    Wadi Al Safa 3 · 21 villas

    Started
    05 Dec 2023
    Current planned completion
    31 Aug 2026

    3 unit and villa sales in the year to Sep 2026

  11. THE LAKESHORE VILLAS BY ELLINGTON
    Registered status: Active
    1.4% complete

    Wadi Al Safa 3 · 38 villas

    Started
    05 Dec 2023
    Current planned completion
    Not published

    2 unit and villa sales in the year to Sep 2026

  12. THE LAKEVIEW VILLAS BY ELLINGTON
    Registered status: Active
    20.1% complete

    Wadi Al Safa 3 · 22 villas

    Started
    11 Oct 2023
    Current planned completion
    30 Aug 2026

    1 unit or villa sale in the year to Sep 2026

22 more projects
  1. THE CRESTMARK
    Registered status: Active
    61.2% complete

    Business Bay · 191 units, 1 building

    Started
    26 Sep 2023
    Current planned completion
    Not published

    23 unit and villa sales in the year to Sep 2026

  2. THE WATERSIDE VILLAS BY ELLINGTON
    Registered status: Active
    45% complete

    Wadi Al Safa 3 · 17 villas

    Started
    21 Jun 2023
    Current planned completion
    30 Jun 2026

    1 unit or villa sale in the year to Sep 2026

  3. UH WEST BY ELLINGTON
    Registered status: Active
    83.7% complete

    Al Thanyah Fifth · 381 units, 1 building

    Started
    26 May 2023
    Current planned completion
    03 Mar 2026

    60 unit and villa sales in the year to Sep 2026

  4. UH EAST BY ELLINGTON
    Registered status: Active
    62.8% complete

    Al Thanyah Fifth · 381 units, 1 building

    Started
    26 May 2023
    Current planned completion
    30 Mar 2026

    62 unit and villa sales in the year to Sep 2026

  5. THE HIGHBURY
    Registered status: Active
    80% complete

    Al Merkadh · 342 units, 1 building

    Started
    17 Apr 2023
    Current planned completion
    Not published

    44 unit and villa sales in the year to Sep 2026

  6. BELMONT RESIDENCES
    Registered status: Finished

    Al Barsha South Fifth · 69 units, 1 building

    Started
    04 Apr 2023
    Current planned completion
    Not published
    Completed
    24 Aug 2026

    6 unit and villa sales in the year to Sep 2026

  7. THE PORTMAN
    Registered status: Active
    78.7% complete

    Al Barsha South Fourth · 167 units, 1 building

    Started
    12 Dec 2022
    Current planned completion
    30 Sep 2025

    14 unit and villa sales in the year to Sep 2026

  8. HAMILTON HOUSE
    Registered status: Finished

    Al Barsha South Fourth · 102 units, 1 building

    Started
    12 Dec 2022
    Current planned completion
    30 Jan 2025
    Completed
    30 Jan 2025

    13 unit and villa sales in the year to Sep 2026

  9. BERKELEY PLACE
    Registered status: Finished

    Al Merkadh · 127 units, 1 building

    Started
    14 Jun 2022
    Current planned completion
    31 Dec 2024
    Completed
    31 Dec 2024

    10 unit and villa sales in the year to Sep 2026

  10. KENSINGTON WATERS
    Registered status: Finished

    Al Merkadh · 281 units, 2 buildings

    Started
    01 Sep 2021
    Current planned completion
    30 Jun 2024
    Completed
    30 Jun 2024

    48 unit and villa sales in the year to Sep 2026

  11. HARRINGTON HOUSE
    Registered status: Finished

    Al Barsha South Fourth · 92 units, 1 building

    Started
    05 Jan 2021
    Current planned completion
    30 Nov 2022
    Completed
    30 Nov 2022

    10 unit and villa sales in the year to Sep 2026

  12. WILTON PARK RESIDENCES
    Registered status: Finished

    Al Merkadh · 320 units, 2 buildings

    Started
    31 Dec 2018
    Current planned completion
    25 Jun 2023
    Completed
    25 Jun 2023

    36 unit and villa sales in the year to Sep 2026

  13. BELGRAVIA SQUARE
    Registered status: Finished

    Al Barsha South Fourth · 225 units, 2 buildings

    Started
    01 May 2018
    Current planned completion
    08 Nov 2023
    Completed
    08 Nov 2023

    24 unit and villa sales in the year to Sep 2026

  14. BELGRAVIA HEIGHTS I
    Registered status: Finished

    Al Barsha South Fourth · 156 units, 1 building

    Started
    01 Nov 2017
    Current planned completion
    30 Oct 2022
    Completed
    30 Oct 2022

    12 unit and villa sales in the year to Sep 2026

  15. BELGRAVIA HEIGHTS II
    Registered status: Finished

    Al Barsha South Fourth · 142 units, 1 building

    Started
    01 Nov 2017
    Current planned completion
    27 Sep 2024
    Completed
    27 Sep 2024

    17 unit and villa sales in the year to Sep 2026

  16. WILTON TERRACES
    Registered status: Finished

    Al Merkadh · 283 units, 2 buildings

    Started
    01 Sep 2017
    Current planned completion
    31 Dec 2021
    Completed
    05 Jan 2022

    44 unit and villa sales in the year to Sep 2026

  17. BELGRAVIA III
    Registered status: Finished

    Al Barsha South Fourth · 260 units, 2 buildings

    Started
    01 Jun 2017
    Current planned completion
    29 Dec 2021
    Completed
    29 Dec 2021

    30 unit and villa sales in the year to Sep 2026

  18. EATON PLACE
    Registered status: Finished

    Al Barsha South Fourth · 110 units, 1 building

    Started
    22 Dec 2016
    Current planned completion
    30 Sep 2019
    Completed
    30 Sep 2019

    14 unit and villa sales in the year to Sep 2026

  19. SOMERSET MEWS
    Registered status: Finished

    Al Barsha South Fourth · 17 villas

    Started
    15 Aug 2016
    Current planned completion
    30 May 2018
    Completed
    30 May 2018

    1 unit or villa sale in the year to Sep 2026

  20. Belgravia 2
    Registered status: Finished

    Al Barsha South Fourth · 188 units, 1 building

    Started
    15 Jul 2016
    Current planned completion
    06 Feb 2019
    Completed
    06 Feb 2019

    19 unit and villa sales in the year to Sep 2026

  21. DT 1
    Registered status: Finished

    Burj Khalifa · 133 units, 1 building

    Started
    01 May 2016
    Current planned completion
    30 Mar 2020
    Completed
    30 Mar 2020

    14 unit and villa sales in the year to Sep 2026

  22. BELGRAVIA
    Registered status: Finished

    Al Barsha South Fourth · 181 units, 1 building

    Started
    26 Nov 2014
    Current planned completion
    11 Apr 2017
    Completed
    11 Apr 2017

    11 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.