Developer
EMAAR PROPERTIES (P.J.S.C)
DLD developer number 555Registered with DLD on 25 Feb 2008
On the DLD projects register
- Projects
- 63
- Live
- 11
- Completed
- 52
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 63 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- The Oasis - Palmiera CollectiveRegistered status: Active1.3% complete
Me'Aisem Second · 37 land plots
- Started
- 03 Jan 2026
- Current planned completion
- 28 Feb 2029
- The Oasis - LavitaRegistered status: Active20.1% complete
Me'Aisem Second · 48 land plots
- Started
- 01 Oct 2024
- Current planned completion
- 31 Jan 2029
- The Oasis - Palmiera 3Registered status: Active72.6% complete
Me'Aisem Second · 58 land plots
- Started
- 22 Aug 2024
- Current planned completion
- 31 Oct 2028
- The Oasis - Palmiera 2Registered status: Active77.1% complete
Me'Aisem Second · 55 land plots
- Started
- 13 Jun 2024
- Current planned completion
- Not published
- The Oasis - MirageRegistered status: Active46.9% complete
Me'Aisem Second · 203 land plots
- Started
- 01 Apr 2024
- Current planned completion
- Not published
- The Oasis - PalmieraRegistered status: Active81.7% complete
Me'Aisem Second · 264 land plots
- Started
- 14 Aug 2023
- Current planned completion
- Not published
- Golf HeightsRegistered status: Finished
Al Thanyah Third · 281 units, 1 building
- Started
- 26 Mar 2023
- Current planned completion
- 31 Dec 2026
- Completed
- 18 Jun 2026
40 unit and villa sales in the year to Sep 2026
- THE RESIDENCE | Burj KhalifaRegistered status: Finished
Burj Khalifa · 35 units, 2 buildings
- Started
- 21 Mar 2023
- Current planned completion
- 31 Dec 2024
- Completed
- 22 Sep 2026
1 unit or villa sale in the year to Sep 2026
- MARINA SHORESRegistered status: Active87.2% complete
Marsa Dubai · 447 units, 1 building
- Started
- 18 Dec 2022
- Current planned completion
- 31 Dec 2026
37 unit and villa sales in the year to Sep 2026
- ARABIAN RANCHES - YASMIN COMMUNITYRegistered status: Finished
Wadi Al Safa 7 · 98 land plots
- Started
- 01 Mar 2015
- Current planned completion
- 01 Jul 2017
- Completed
- 01 Jul 2017
2 unit and villa sales in the year to Sep 2026
- ARABIAN RANCHES - RASHA COMMUNITYRegistered status: Finished
Wadi Al Safa 7 · 1 villa, 140 land plots
- Started
- 01 Jan 2015
- Current planned completion
- 01 Jun 2017
- Completed
- 01 Jun 2017
4 unit and villa sales in the year to Sep 2026
- ARABIAN RANCHES- ROSA COMMUNITYRegistered status: Finished
Wadi Al Safa 7 · 144 land plots
- Started
- 01 Dec 2014
- Current planned completion
- 15 Oct 2016
- Completed
- 15 Oct 2016
2 unit and villa sales in the year to Sep 2026
51 more projects
- Arabian Ranches - Lila CommunityRegistered status: Finished
Wadi Al Safa 7 · 219 land plots
- Started
- 01 Nov 2014
- Current planned completion
- 01 Feb 2017
- Completed
- 01 Feb 2017
14 unit and villa sales in the year to Sep 2026
- ARABIAN RANCHES - PALMA COMMUNITYRegistered status: Finished
Wadi Al Safa 7 · 121 land plots
- Started
- 02 Feb 2014
- Current planned completion
- 10 Feb 2016
- Completed
- 31 Mar 2016
12 unit and villa sales in the year to Sep 2026
- Arabian Ranches-Casa CommunityRegistered status: Finished
Wadi Al Safa 7 · 1 villa, 253 land plots
- Started
- 01 Apr 2013
- Current planned completion
- 31 Dec 2014
- Completed
- 31 Dec 2014
19 unit and villa sales in the year to Sep 2026
- THE ADDRESS - THE BLVDRegistered status: Finished
Burj Khalifa · 543 units, 1 building
- Started
- 01 Nov 2012
- Current planned completion
- 26 Mar 2017
- Completed
- 26 Mar 2017
48 unit and villa sales in the year to Sep 2026
- ALMA-2Registered status: Finished
Wadi Al Safa 6 · 62 villas, 19 land plots
- Started
- 01 Sep 2012
- Current planned completion
- 13 Feb 2013
- Completed
- 13 Feb 2014
1 unit or villa sale in the year to Sep 2026
- LA AVENIDA-2Registered status: Finished
Wadi Al Safa 6 · 33 land plots
- Started
- 27 Jun 2012
- Current planned completion
- 21 Aug 2014
- Completed
- 21 Aug 2014
2 unit and villa sales in the year to Sep 2026
- PANORAMARegistered status: Finished
Al Thanyah Third · 233 units, 2 buildings
- Started
- 16 May 2012
- Current planned completion
- 04 Jan 2015
- Completed
- 04 Jan 2015
8 unit and villa sales in the year to Sep 2026
- DD STAND POINTRegistered status: Finished
Burj Khalifa · 537 units, 3 buildings
- Started
- 24 Apr 2012
- Current planned completion
- 12 Dec 2012
- Completed
- 12 Dec 2012
35 unit and villa sales in the year to Sep 2026
- BD BOULEVARD PLAZARegistered status: Finished
Burj Khalifa · 217 units, 3 buildings
- Started
- 14 Feb 2012
- Current planned completion
- 13 Jan 2012
- Completed
- 22 Feb 2012
9 unit and villa sales in the year to Sep 2026
- DM MARINA PLAZARegistered status: Finished
Marsa Dubai · 170 units, 1 building
- Started
- 14 Feb 2012
- Current planned completion
- 06 Oct 2011
- Completed
- 06 Oct 2011
18 unit and villa sales in the year to Sep 2026
- BURJ DUBAIRegistered status: Finished
Burj Khalifa · 28 units, 2 buildings, 4 land plots
- Started
- 21 Apr 2009
- Current planned completion
- 18 Jul 2011
- Completed
- 18 Jul 2011
- 29 BOULEVARDRegistered status: Finished
Burj Khalifa · 750 units, 3 buildings
- Started
- 26 Aug 2008
- Current planned completion
- 10 Apr 2013
- Completed
- 10 Apr 2013
79 unit and villa sales in the year to Sep 2026
- GOLF HOMESRegistered status: Finished
Wadi Al Safa 6 · 1 villa
- Started
- 25 Jun 2008
- Current planned completion
- 19 May 2013
- Completed
- 30 Jun 2011
- CLAREN 1Registered status: Finished
Burj Khalifa · 321 units, 3 buildings
- Started
- 06 May 2008
- Current planned completion
- 30 Nov 2011
- Completed
- 12 Jul 2012
25 unit and villa sales in the year to Sep 2026
- POLO HOMESRegistered status: Finished
Al Hebiah Second · 69 land plots
- Started
- 08 Apr 2008
- Current planned completion
- 01 Jun 2014
- Completed
- 31 Aug 2011
5 unit and villa sales in the year to Sep 2026
- Arabian Ranches -La Avenida IRegistered status: Finished
Wadi Al Safa 6 · 1 villa, 16 land plots
- Started
- 04 Jan 2008
- Current planned completion
- 04 Jan 2009
- Completed
- 04 Jan 2009
- DD BOULEVARD CENTRALRegistered status: Finished
Burj Khalifa · 424 units, 4 buildings
- Started
- 03 Jul 2007
- Current planned completion
- 14 Aug 2012
- Completed
- 14 Aug 2012
36 unit and villa sales in the year to Sep 2026
- Arabian Ranches - Alvorada IIIRegistered status: Finished
Wadi Al Safa 6 · 61 villas, 60 land plots
- Started
- 29 May 2007
- Current planned completion
- 29 May 2008
- Completed
- 29 May 2008
5 unit and villa sales in the year to Sep 2026
- MOSELARegistered status: Finished
Al Thanyah Third · 351 units, 1 building
- Started
- 01 May 2007
- Current planned completion
- 01 Sep 2010
- Completed
- 01 Sep 2010
18 unit and villa sales in the year to Sep 2026
- TANARORegistered status: Finished
Al Thanyah Third · 249 units, 1 building
- Started
- 01 May 2007
- Current planned completion
- 01 Sep 2010
- Completed
- 01 Sep 2010
23 unit and villa sales in the year to Sep 2026
- DLD project 1021Registered status: Finished
Wadi Al Safa 6
- Started
- 30 Mar 2007
- Current planned completion
- 30 Mar 2008
- Completed
- 30 Mar 2008
- PARK ISLANDSRegistered status: Finished
Marsa Dubai · 733 units, 1 villa, 7 buildings
- Started
- 01 Jul 2006
- Current planned completion
- 01 Mar 2010
- Completed
- 01 Mar 2010
79 unit and villa sales in the year to Sep 2026
- BURJ VIEWSRegistered status: Finished
Burj Khalifa · 737 units, 4 buildings
- Started
- 01 Mar 2006
- Current planned completion
- 01 Sep 2009
- Completed
- 01 Sep 2009
47 unit and villa sales in the year to Sep 2026
- MARINA QUAYSRegistered status: Finished
Marsa Dubai · 450 units, 7 buildings
- Started
- 01 Mar 2006
- Current planned completion
- 01 Jan 2010
- Completed
- 01 Jan 2010
28 unit and villa sales in the year to Sep 2026
- DUBAI MARINA MALLRegistered status: Finished
Marsa Dubai · 452 units, 3 buildings
- Started
- 01 Mar 2006
- Current planned completion
- 01 Dec 2009
- Completed
- 01 Dec 2009
40 unit and villa sales in the year to Sep 2026
- The Lakes ZulalRegistered status: Finished
Al Thanyah Third · 306 villas, 80 land plots
- Started
- 01 Jan 2006
- Current planned completion
- 01 Jan 2006
- Completed
- 01 Nov 2009
12 unit and villa sales in the year to Sep 2026
- THE DUBAI MALLRegistered status: Finished
Burj Khalifa · 456 units, 3 buildings
- Started
- 01 Oct 2004
- Current planned completion
- 01 Aug 2008
- Completed
- 01 Aug 2008
34 unit and villa sales in the year to Sep 2026
- BURJ KHALIFA TOWERSRegistered status: Finished
Burj Khalifa · 1,078 units, 1 building
- Started
- 01 Jan 2004
- Current planned completion
- 01 Jan 2012
- Completed
- 01 Jan 2012
118 unit and villa sales in the year to Sep 2026
- The Lakes GhadeerRegistered status: Finished
Al Thanyah Third · 138 villas, 48 land plots
- Started
- 01 Jan 2004
- Current planned completion
- 01 Jan 2007
- Completed
- 01 Jan 2007
8 unit and villa sales in the year to Sep 2026
- DLD project 4577Registered status: Pending100% complete
Al Thanayah Fourth
- Started
- 22 Jun 2003
- Current planned completion
- 07 Oct 2005
- Emirates Living - Springs 1Registered status: Finished
Al Thanayah Fourth · 242 villas, 71 land plots
- Started
- 01 Jan 2002
- Current planned completion
- 01 Feb 2005
- Completed
- 01 Feb 2005
22 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 2Registered status: Finished
Al Thanayah Fourth · 484 villas, 114 land plots
- Started
- 01 Jan 2002
- Current planned completion
- 01 Feb 2005
- Completed
- 01 Feb 2005
26 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 12Registered status: Finished
Al Thanayah Fourth · 308 villas, 79 land plots
- Started
- 01 Jan 2002
- Current planned completion
- 01 Jan 2005
- Completed
- 01 Jan 2005
25 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 8Registered status: Finished
Al Thanayah Fourth · 304 villas, 84 land plots
- Started
- 01 Jan 2002
- Current planned completion
- 01 Jan 2005
- Completed
- 01 Jan 2005
28 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 9Registered status: Finished
Al Thanayah Fourth · 318 villas, 86 land plots
- Started
- 01 Jan 2002
- Current planned completion
- 01 Jan 2005
- Completed
- 01 Jan 2005
28 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 10Registered status: Finished
Al Thanayah Fourth · 322 villas, 85 land plots
- Started
- 01 Jan 2002
- Current planned completion
- 01 Jan 2005
- Completed
- 01 Jan 2005
32 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 3Registered status: Finished
Al Thanayah Fourth · 450 villas, 129 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Jan 2004
- Completed
- 01 Jan 2004
30 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 4Registered status: Finished
Al Thanayah Fourth · 320 villas, 84 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Jan 2004
- Completed
- 01 Apr 2004
24 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 5Registered status: Finished
Al Thanayah Fourth · 272 villas, 68 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Dec 2004
- Completed
- 01 Dec 2004
19 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 15Registered status: Finished
Al Thanayah Fourth · 478 villas, 141 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Oct 2004
- Completed
- 01 Oct 2004
27 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 14Registered status: Finished
Al Thanayah Fourth · 408 villas, 98 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Oct 2004
- Completed
- 01 Oct 2004
31 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 11Registered status: Finished
Al Thanayah Fourth · 484 villas, 119 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Oct 2004
- Completed
- 29 May 2008
37 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 6Registered status: Finished
Al Thanayah Fourth · 197 villas, 66 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Dec 2004
- Completed
- 01 Dec 2004
12 unit and villa sales in the year to Sep 2026
- Emirates Living - Springs 7Registered status: Finished
Al Thanayah Fourth · 268 villas, 71 land plots
- Started
- 01 Jan 2001
- Current planned completion
- 01 Sep 2004
- Completed
- 01 Sep 2004
30 unit and villa sales in the year to Sep 2026
- The Lakes - Deema 1Registered status: Finished
Al Thanyah Third · 65 villas, 65 land plots
- Started
- 01 Jan 2000
- Current planned completion
- 01 Jan 2003
- Completed
- 01 Jan 2003
1 unit or villa sale in the year to Sep 2026
- The Lakes Deema 3Registered status: Finished
Al Thanyah Third · 53 villas, 54 land plots
- Started
- 01 Jan 2000
- Current planned completion
- 01 Jan 2003
- Completed
- 01 Jan 2003
2 unit and villa sales in the year to Sep 2026
- The Lakes Deema 2Registered status: Finished
Al Thanyah Third · 50 villas, 52 land plots
- Started
- 01 Jan 2000
- Current planned completion
- 01 Jan 2003
- Completed
- 01 Jan 2003
1 unit or villa sale in the year to Sep 2026
- The Lakes Deema 4Registered status: Finished
Al Thanyah Third · 56 villas, 56 land plots
- Started
- 01 Jan 2000
- Current planned completion
- 01 Jan 2003
- Completed
- 01 Jan 2003
5 unit and villa sales in the year to Sep 2026
- Emirates HillsRegistered status: Finished100% complete
Al Thanayah Fourth · 75 villas, 631 land plots
- Started
- 01 Jan 1998
- Current planned completion
- 28 Aug 2000
12 unit and villa sales in the year to Sep 2026
- DLD project 1465Registered status: Pending
Burj Khalifa
- Started
- Not published
- Current planned completion
- Not published
- DLD project 1466Registered status: Pending
Burj Khalifa
- Started
- Not published
- Current planned completion
- Not published
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.