Developer
ESK INVESTMENTS - SOLE PROPRIETORSHIP L.L.C - DUBAI BRANCH
DLD developer number 2454Registered with DLD on 04 Aug 2025
On the DLD projects register
- Projects
- 1
- Live
- 1
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 1 project.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 14 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- AJWAN RESIDENCESRegistered status: Active10% complete
Madinat Al Mataar · 122 units, 1 building
- Started
- 27 Dec 2025
- Current planned completion
- 27 Jan 2028