Developer
FAKHRUDDIN PROPERTIES DEVELOPMENT L.L.C
DLD developer number 1415Registered with DLD on 17 Mar 2022
On the DLD projects register
- Projects
- 6
- Live
- 6
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 2
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 6 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4539Registered status: Not started0% complete
Wadi Al Safa 5 · 463 units, 1 building
- Started
- 01 Jan 2027
- Current planned completion
- 31 May 2029
- DLD project 4345Registered status: Not started0% complete
Palm Deira · 65 units, 1 building
- Started
- 01 Jul 2026
- Current planned completion
- 15 Dec 2028
- TREPPAN SERENIQUE RESIDENCESRegistered status: Active5.2% complete
Palm Deira · 164 units, 2 buildings
- Started
- 15 Oct 2025
- Current planned completion
- 15 Oct 2027
44 unit and villa sales in the year to Sep 2026
- TREPPAN TOWERRegistered status: Active11.9% complete
Al Barsha South Fifth · 263 units, 1 building
- Started
- 01 Jan 2025
- Current planned completion
- 01 Apr 2027
92 unit and villa sales in the year to Sep 2026
- HATIMI RESIDENCES BY FAKHRUDDINRegistered status: Active50.8% complete
Palm Deira · 116 units, 1 building
- Started
- 02 Oct 2024
- Current planned completion
- 02 Oct 2026
11 unit and villa sales in the year to Sep 2026
- Maimoon GardensRegistered status: Active78% complete
Al Barsha South Fourth · 722 units, 3 buildings
- Started
- 01 Dec 2022
- Current planned completion
- 31 Dec 2025
45 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.