Developer
G F S REAL ESTATE L.L.C
DLD developer number 2053Registered with DLD on 12 Sep 2024
On the DLD projects register
- Projects
- 7
- Live
- 7
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 4
A planned completion date moved once since we started checking in Oct 2026, on 1 of 7 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4515Registered status: Not started0% complete
Saih Shuaib 2 · 312 units, 1 building
- Started
- 01 Oct 2026
- Current planned completion
- 01 Apr 2029
- Coventry CentroRegistered status: Not started0% complete
Saih Shuaib 2 · 264 units, 1 building
- Started
- 01 Jul 2026
- Current planned completion
- 01 Jul 2028
7 unit and villa sales in the year to Sep 2026
- Coventry CoveRegistered status: Not started0% complete
Saih Shuaib 2 · 255 units, 1 building
- Started
- 01 Jul 2026
- Current planned completion
- 01 Jul 2029
2 unit and villa sales in the year to Sep 2026
- Coventry CurveRegistered status: Not started0% complete
Saih Shuaib 2 · 246 units, 1 building
- Started
- 01 Mar 2026
- Current planned completion
- 15 Jun 2028
21 unit and villa sales in the year to Sep 2026
- Coventry Residence 3Registered status: Not started0% complete
Saih Shuaib 2 · 185 units, 1 building
- Started
- 15 Dec 2025
- Current planned completion
- 31 Dec 2027
Planned date moved once since we started checking in Oct 2026
14 unit and villa sales in the year to Sep 2026
- Coventry ResidenceRegistered status: Not started0% complete
Saih Shuaib 2 · 163 units, 1 building
- Started
- 30 Sep 2025
- Current planned completion
- 30 Nov 2027
5 unit and villa sales in the year to Sep 2026
- Coventry GardensRegistered status: Active1.2% complete
Wadi Al Safa 5 · 97 units, 1 building
- Started
- 15 Dec 2024
- Current planned completion
- 14 Mar 2027
11 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.