7
Live
4
Completed
3
Cancelled
0
Planned completion in the next 12 months
2
Started in 2026
1

No planned completion date has moved since we started checking in Oct 2026, across 7 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Beverly Crown
    Registered status: Not started
    0% complete

    Al Barsha South Fourth · 214 units, 1 building

    Started
    10 Nov 2026
    Current planned completion
    31 Dec 2028

    1 unit or villa sale in the year to Sep 2026

  2. Beverly Park
    Registered status: Active
    6.8% complete

    Wadi Al Safa 5 · 159 units, 1 building

    Started
    31 Oct 2025
    Current planned completion
    31 Oct 2027

    54 unit and villa sales in the year to Sep 2026

  3. Beverly Grande
    Registered status: Not started
    0.5% complete

    Al Hebiah First · 296 units, 1 building

    Started
    15 Aug 2025
    Current planned completion
    31 Dec 2027

    142 unit and villa sales in the year to Sep 2026

  4. One Beverly
    Registered status: Active
    72.9% complete

    Al Barshaa South Third · 389 units, 1 building

    Started
    01 Dec 2024
    Current planned completion
    01 Dec 2026

    135 unit and villa sales in the year to Sep 2026

  5. Beverly Residence 2
    Registered status: Finished

    Al Barsha South Fourth · 108 units, 1 building

    Started
    01 Jun 2023
    Current planned completion
    Not published
    Completed
    04 Jun 2026

    18 unit and villa sales in the year to Sep 2026

  6. BEVERLY BOULEVARD
    Registered status: Finished

    Al Barshaa South Third · 271 units, 1 building

    Started
    01 Oct 2022
    Current planned completion
    30 Sep 2024
    Completed
    30 Sep 2024

    45 unit and villa sales in the year to Sep 2026

  7. Beverly Residence
    Registered status: Finished

    Al Barsha South Fourth · 195 units, 1 building

    Started
    01 Jun 2017
    Current planned completion
    31 May 2020
    Completed
    11 Feb 2021

    18 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.