Developer
IMTIAZ SUNSET REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 2157Registered with DLD on 29 Nov 2024
On the DLD projects register
- Projects
- 3
- Live
- 3
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 3
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 3 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- SUNSET BAY FOUR BY IMTIAZRegistered status: Active53% complete
Palm Deira · 63 units, 1 building
- Started
- 15 May 2025
- Current planned completion
- 15 May 2027
18 unit and villa sales in the year to Sep 2026
- SUNSET BAY THREE BY IMTIAZRegistered status: Active60% complete
Palm Deira · 63 units, 1 building
- Started
- 20 Mar 2025
- Current planned completion
- 20 Mar 2027
10 unit and villa sales in the year to Sep 2026
- Sunset Bay One By ImtiazRegistered status: Active78% complete
Palm Deira · 66 units, 1 building
- Started
- 25 Dec 2024
- Current planned completion
- 25 Dec 2026
4 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.