Developer
ISLAND OASIS PROPERTIES
DLD developer number 921Registered with DLD on 19 Oct 2011
On the DLD projects register
- Projects
- 36
- Live
- 27
- Completed
- 9
- Cancelled
- 0
- Planned completion in the next 12 months
- 4
- Started in 2026
- 3
No planned completion date has moved since we started checking in Oct 2026, across 36 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- PIAZZA ROMARegistered status: Not started0.2% complete
Al Hebiah Fifth · 336 units, 4 buildings
- Started
- 30 Jul 2026
- Current planned completion
- 30 Jun 2030
41 unit and villa sales in the year to Sep 2026
- DLD project 4381Registered status: Not started0.3% complete
Al Hebiah Fifth · 754 units, 4 buildings
- Started
- 15 Jul 2026
- Current planned completion
- 31 Jan 2030
- DLD project 4382Registered status: Not started0.3% complete
Al Hebiah Fifth · 682 units, 4 buildings
- Started
- 15 Jul 2026
- Current planned completion
- 31 Jan 2030
- DAMAC LAGOONS - LAGOON VIEWS 13Registered status: Active6% complete
Al Hebiah Fifth · 1,509 units, 4 buildings, 1 land plot
- Started
- 18 Nov 2024
- Current planned completion
- 31 Dec 2027
516 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 12Registered status: Active36.5% complete
Al Hebiah Fifth · 322 units, 4 buildings, 1 land plot
- Started
- 18 Nov 2024
- Current planned completion
- 30 Jun 2027
19 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - VALENCIARegistered status: Active5.2% complete
Al Hebiah Fifth · 1,558 units, 4 buildings, 1 land plot
- Started
- 05 Nov 2024
- Current planned completion
- 28 Feb 2028
1,260 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 11Registered status: Active42.6% complete
Al Hebiah Fifth · 322 units, 4 buildings, 1 land plot
- Started
- 17 Oct 2024
- Current planned completion
- 30 Jun 2027
14 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 9Registered status: Active47.3% complete
Al Hebiah Fifth · 108 units, 2 buildings
- Started
- 21 Aug 2024
- Current planned completion
- 31 Mar 2027
1 unit or villa sale in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 10Registered status: Active47.4% complete
Al Hebiah Fifth · 108 units, 2 buildings
- Started
- 21 Aug 2024
- Current planned completion
- 31 Mar 2027
4 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 8Registered status: Active41.5% complete
Al Hebiah Fifth · 96 units, 2 buildings
- Started
- 05 Jul 2024
- Current planned completion
- Not published
4 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 3Registered status: Active39.2% complete
Al Hebiah Fifth · 162 units, 3 buildings
- Started
- 23 Apr 2024
- Current planned completion
- Not published
2 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 4Registered status: Active42.2% complete
Al Hebiah Fifth · 144 units, 3 buildings
- Started
- 22 Apr 2024
- Current planned completion
- Not published
1 unit or villa sale in the year to Sep 2026
24 more projects
- DAMAC LAGOONS - LAGOON VIEWS 5Registered status: Active42.3% complete
Al Hebiah Fifth · 48 units, 1 building
- Started
- 22 Apr 2024
- Current planned completion
- Not published
2 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 6Registered status: Active41.8% complete
Al Hebiah Fifth · 48 units, 1 building
- Started
- 22 Apr 2024
- Current planned completion
- Not published
- DAMAC LAGOONS - LAGOON VIEWS 7Registered status: Active44.9% complete
Al Hebiah Fifth · 96 units, 2 buildings
- Started
- 22 Apr 2024
- Current planned completion
- Not published
1 unit or villa sale in the year to Sep 2026
- DAMAC LAGOONS - LAGOON VIEWS 1Registered status: Active55.6% complete
Al Hebiah Fifth · 162 units, 3 buildings
- Started
- 06 Apr 2024
- Current planned completion
- Not published
- DAMAC LAGOONS - LAGOON VIEWS 2Registered status: Active52.3% complete
Al Hebiah Fifth · 162 units, 3 buildings
- Started
- 06 Apr 2024
- Current planned completion
- Not published
3 unit and villa sales in the year to Sep 2026
- DAMAC LAGOONS - MOROCCO 1Registered status: Active76.9% complete
Al Hebiah Fifth · 470 land plots
- Started
- 29 Aug 2023
- Current planned completion
- Not published
- DAMAC LAGOONS - MOROCCO 2Registered status: Active65.3% complete
Al Hebiah Fifth · 553 land plots
- Started
- 29 Aug 2023
- Current planned completion
- Not published
- DAMAC LAGOONS - MYKONOSRegistered status: Active81.1% complete
Al Hebiah Fifth · 575 land plots
- Started
- 12 Feb 2023
- Current planned completion
- 31 Dec 2025
- DAMAC LAGOONS - MARBELLARegistered status: Active87.3% complete
Al Hebiah Fifth · 608 land plots
- Started
- 12 Feb 2023
- Current planned completion
- 31 Dec 2025
- DAMAC LAGOONS - VENICE (1)Registered status: Active74.4% complete
Al Hebiah Fifth · 423 land plots
- Started
- 28 Dec 2022
- Current planned completion
- 29 Sep 2025
- DAMAC LAGOONS - MALTA (1)Registered status: Finished
Al Hebiah Fifth · 759 land plots
- Started
- 23 Aug 2022
- Current planned completion
- 29 Sep 2025
- Completed
- 19 Jun 2026
- DAMAC LAGOONS - MALTA (2)Registered status: Finished
Al Hebiah Fifth · 366 land plots
- Started
- 23 Aug 2022
- Current planned completion
- 29 Sep 2025
- Completed
- 08 Apr 2026
- DAMAC LAGOONS - PORTOFINORegistered status: Active97.1% complete
Al Hebiah Fifth · 878 land plots
- Started
- 24 Apr 2022
- Current planned completion
- 29 Jun 2025
- DAMAC LAGOONS - COSTA BRAVA (1)Registered status: Finished
Al Hebiah Fifth · 554 land plots
- Started
- 28 Feb 2022
- Current planned completion
- 29 Jul 2025
- Completed
- 10 Apr 2026
- DAMAC LAGOONS - COSTA BRAVA (2)Registered status: Finished
Al Hebiah Fifth · 496 land plots
- Started
- 28 Feb 2022
- Current planned completion
- 29 Jul 2025
- Completed
- 04 Aug 2026
- DAMAC LAGOONS - NICE 1Registered status: Active93.7% complete
Al Hebiah Fifth · 550 land plots
- Started
- 28 Feb 2022
- Current planned completion
- 29 Jul 2025
- DAMAC LAGOONS - NICE 2Registered status: Active83.9% complete
Al Hebiah Fifth · 451 land plots
- Started
- 28 Feb 2022
- Current planned completion
- 29 Jul 2025
- DAMAC LAGOONS - IBIZARegistered status: Active78.9% complete
Al Hebiah Fifth · 822 land plots
- Started
- 12 Feb 2022
- Current planned completion
- 31 Dec 2025
- DAMAC LAGOONS - MONTE CARLORegistered status: Active86.4% complete
Al Hebiah Fifth · 423 land plots
- Started
- 12 Feb 2022
- Current planned completion
- 31 Dec 2025
- DAMAC LAGOONS - SANTORINI (3)Registered status: Finished
Al Hebiah Fifth · 95 land plots
- Started
- 27 Jan 2022
- Current planned completion
- 29 Jul 2025
- Completed
- 09 Apr 2026
- DAMAC LAGOONS - SANTORINI (1)Registered status: Finished
Al Hebiah Fifth · 458 land plots
- Started
- 06 Jan 2022
- Current planned completion
- 29 Jul 2025
- Completed
- 29 Jul 2025
- DAMAC LAGOONS - SANTORINI (2)Registered status: Finished
Al Hebiah Fifth · 387 land plots
- Started
- 06 Jan 2022
- Current planned completion
- 29 Jul 2025
- Completed
- 11 Feb 2026
- ZADA TOWERRegistered status: Finished
Business Bay · 703 units, 1 building
- Started
- 15 Apr 2019
- Current planned completion
- 30 Jun 2023
- Completed
- 30 Jun 2023
55 unit and villa sales in the year to Sep 2026
- GREEN PARKRegistered status: Finished
Al Barsha South Fifth · 209 units, 1 building
- Started
- 01 May 2010
- Current planned completion
- 25 Nov 2013
- Completed
- 25 Nov 2013
12 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.