Developer
JUMEIRAH GOLF ESTATES L.L.C
DLD developer number 108Registered with DLD on 10 Jan 2007
On the DLD projects register
- Projects
- 11
- Live
- 0
- Completed
- 11
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 11 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Alandalus Building GRegistered status: Finished
Me'Aisem First · 29 units, 1 building
- Started
- 04 Feb 2018
- Current planned completion
- 28 Apr 2021
- Completed
- 28 Apr 2021
6 unit and villa sales in the year to Sep 2026
- DLD project 2022Registered status: Finished
Me'Aisem First · 89 units
- Started
- 01 Jan 2018
- Current planned completion
- 31 Aug 2020
- Completed
- 31 Aug 2020
- ALandalus TownhouseRegistered status: Finished
Me'Aisem First · 95 land plots
- Started
- 01 Aug 2017
- Current planned completion
- 05 Oct 2020
- Completed
- 30 Apr 2020
7 unit and villa sales in the year to Sep 2026
- ALandalus Building DRegistered status: Finished
Me'Aisem First · 136 units, 1 building
- Started
- 15 May 2017
- Current planned completion
- 04 Apr 2020
- Completed
- 04 Apr 2020
13 unit and villa sales in the year to Sep 2026
- AL Andalus Phase 2Registered status: Finished
Me'Aisem First · 120 units, 1 building
- Started
- 15 Sep 2016
- Current planned completion
- 31 Dec 2019
- Completed
- 31 Dec 2019
9 unit and villa sales in the year to Sep 2026
- Redwood Park Phase2Registered status: Finished
Me'Aisem First · 40 land plots
- Started
- 09 Jun 2016
- Current planned completion
- 07 Sep 2017
- Completed
- 07 Sep 2017
- RED WOOD PARKRegistered status: Finished
Me'Aisem First · 35 land plots
- Started
- 01 Jan 2015
- Current planned completion
- 06 Nov 2016
- Completed
- 31 Jul 2018
3 unit and villa sales in the year to Sep 2026
- ALANDALUSRegistered status: Finished
Me'Aisem First · 215 units, 2 buildings
- Started
- 14 Aug 2014
- Current planned completion
- 28 Feb 2019
- Completed
- 15 Jun 2018
18 unit and villa sales in the year to Sep 2026
- JUMEIRAH GOLF ESTATESRegistered status: Finished
Me'Aisem First · 2 buildings, 407 land plots
- Started
- 27 Sep 2010
- Current planned completion
- 31 Oct 2012
- Completed
- 30 Aug 2015
14 unit and villa sales in the year to Sep 2026
- FLAME TREE RIDGERegistered status: Finished
Me'Aisem First · 32 land plots
- Started
- 01 May 2008
- Current planned completion
- 19 Jul 2016
- Completed
- 19 Jul 2016
2 unit and villa sales in the year to Sep 2026
- REDWOOD AVENUERegistered status: Finished
Me'Aisem First · 49 land plots
- Started
- 01 May 2008
- Current planned completion
- 31 Dec 2015
- Completed
- 31 Dec 2016
6 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.