Developer

LEOS DEVELOPMENT L.L.C

DLD developer number 1494Registered with DLD on 05 Oct 2022

On the DLD projects register

Projects
9
Live
7
Completed
2
Cancelled
0
Planned completion in the next 12 months
3
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 9 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4528
    Registered status: Pending
    0% complete

    Umm Addamin

    Started
    15 Mar 2027
    Current planned completion
    25 Sep 2029
  2. Hadley Heights 2
    Registered status: Not started
    0% complete

    Al Hebiah Fourth · 230 units, 1 building

    Started
    20 Oct 2025
    Current planned completion
    20 Oct 2027

    192 unit and villa sales in the year to Sep 2026

  3. Weybridge Gardens 5
    Registered status: Not started
    0% complete

    Wadi Al Safa 5 · 168 units, 1 building

    Started
    01 Sep 2025
    Current planned completion
    15 Sep 2027

    135 unit and villa sales in the year to Sep 2026

  4. Kensington Gardens
    Registered status: Not started
    0% complete

    Wadi Al Safa 5 · 361 units, 1 building

    Started
    25 Jun 2025
    Current planned completion
    27 Sep 2027

    320 unit and villa sales in the year to Sep 2026

  5. Weybridge Gardens 3
    Registered status: Active
    23.9% complete

    Wadi Al Safa 5 · 208 units, 1 building

    Started
    20 Dec 2024
    Current planned completion
    20 Aug 2026

    26 unit and villa sales in the year to Sep 2026

  6. Weybridge Gardens 2
    Registered status: Active
    33.7% complete

    Wadi Al Safa 5 · 288 units, 1 building

    Started
    14 Oct 2024
    Current planned completion
    Not published

    27 unit and villa sales in the year to Sep 2026

  7. Cavendish Square
    Registered status: Active
    4.6% complete

    Al Barsha South Fifth · 141 units, 1 building

    Started
    07 Jan 2024
    Current planned completion
    Not published

    12 unit and villa sales in the year to Sep 2026

  8. Weybridge Gardens
    Registered status: Finished

    Wadi Al Safa 5 · 187 units, 1 building

    Started
    15 Oct 2023
    Current planned completion
    Not published
    Completed
    08 Sep 2026

    15 unit and villa sales in the year to Sep 2026

  9. Hadley Heights
    Registered status: Finished

    Al Barsha South Fourth · 219 units, 1 building

    Started
    01 May 2023
    Current planned completion
    30 Nov 2025
    Completed
    02 Oct 2025

    32 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.