Dubai Land Department records

Developer

MAJID AL FUTTAIM GHAF WOODS L.L.C

DLD developer number 1441Registered with DLD on 21 Jun 2022

On the DLD projects register

Projects
7
Live
7
Completed
0
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 7 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4520
    Registered status: Not started
    0% complete

    Wadi Al Safa 4 · 348 units, 1 building

    Started
    15 Aug 2027
    Current planned completion
    15 Dec 2029
  2. CAPRIA EAST
    Registered status: Active
    0.9% complete

    Wadi Al Safa 4 · 553 units, 9 buildings

    Started
    15 Sep 2025
    Current planned completion
    15 May 2029

    153 unit and villa sales in the year to Sep 2026

  3. CAPRIA WEST
    Registered status: Active
    1.2% complete

    Wadi Al Safa 4 · 714 units, 12 buildings

    Started
    15 Aug 2025
    Current planned completion
    08 May 2029

    165 unit and villa sales in the year to Sep 2026

  4. DISTRIKT
    Registered status: Active
    8.4% complete

    Wadi Al Safa 4 · 550 units, 5 buildings

    Started
    01 Aug 2025
    Current planned completion
    30 Sep 2028

    387 unit and villa sales in the year to Sep 2026

  5. Cilia
    Registered status: Active
    43.8% complete

    Wadi Al Safa 4 · 546 units, 10 buildings

    Started
    27 Dec 2024
    Current planned completion
    Not published

    22 unit and villa sales in the year to Sep 2026

  6. Serra
    Registered status: Active
    42.1% complete

    Wadi Al Safa 4 · 535 units, 10 buildings

    Started
    27 Dec 2024
    Current planned completion
    Not published

    86 unit and villa sales in the year to Sep 2026

  7. Lacina
    Registered status: Active
    20.8% complete

    Wadi Al Safa 4 · 324 units, 3 buildings

    Started
    01 Dec 2024
    Current planned completion
    30 Dec 2027

    6 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.