Dubai Land Department records

Developer

MAK DEVELOPERS L.L.C

DLD developer number 1757Registered with DLD on 26 Oct 2023

On the DLD projects register

Projects
2
Live
2
Completed
0
Cancelled
0
Planned completion in the next 12 months
2
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 2 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Saddlewood Park
    Registered status: Active
    12.5% complete

    Nad Al Shiba First · 62 units, 1 building

    Started
    01 Dec 2025
    Current planned completion
    30 Sep 2027

    18 unit and villa sales in the year to Sep 2026

  2. DLD project 3096
    Registered status: Active
    27.2% complete

    Al Barsha South Fourth · 207 units, 1 building

    Started
    05 Sep 2024
    Current planned completion
    05 Sep 2027

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.