Developer
MALINA W1 REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 1672Registered with DLD on 27 Jul 2023
On the DLD projects register
- Projects
- 1
- Live
- 1
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
A planned completion date moved once since we started checking in Oct 2026, on 1 of 1 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- W1Registered status: Active70.2% complete
Jabal Ali First · 83 units, 1 building
- Started
- 14 Mar 2024
- Current planned completion
- 30 Apr 2026
Planned date moved once since we started checking in Oct 2026
Source: DLD projects register, read 11 Nov 2026.