MASHRIQ ELITE REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 1542Registered with DLD on 04 Jan 2023

On the DLD projects register

Projects
6
Live
5
Completed
1
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
1

No planned completion date has moved since we started checking in Oct 2026, across 6 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 12 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Floarea Breeze
    Registered status: Active
    3.8% complete

    Palm Deira · 52 units, 1 building

    Started
    01 Jan 2026
    Current planned completion
    30 Jun 2028

    19 unit and villa sales in the year to Sep 2026

  2. Floarea Skies
    Registered status: Active
    4.5% complete

    Al Barsha South Fourth · 195 units, 1 building

    Started
    01 Aug 2025
    Current planned completion
    31 Dec 2028

    158 unit and villa sales in the year to Sep 2026

  3. FLOAREA OASIS
    Registered status: Active
    12.6% complete

    Wadi Al Safa 5 · 257 units, 1 building

    Started
    30 Jul 2025
    Current planned completion
    30 Dec 2028

    175 unit and villa sales in the year to Sep 2026

  4. Floarea Grande
    Registered status: Active
    48.2% complete

    Al Barshaa South Third · 222 units, 1 building

    Started
    15 Feb 2025
    Current planned completion
    14 Aug 2027

    19 unit and villa sales in the year to Sep 2026

  5. Floarea Vista
    Registered status: Active
    63% complete

    Jabal Ali First · 158 units, 1 building

    Started
    15 Jun 2024
    Current planned completion
    14 Jun 2026

    6 unit and villa sales in the year to Sep 2026

  6. Floarea Residence
    Registered status: Finished

    Al Barshaa South Third · 206 units, 1 building

    Started
    24 Mar 2023
    Current planned completion
    01 Apr 2025
    Completed
    19 Aug 2025

    54 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 12 Nov 2026.