Dubai Land Department records

Developer

ME DO RE DEVELOPMENTS DMCC

DLD developer number 1295Registered with DLD on 02 Jul 2020

On the DLD projects register

Projects
1
Live
1
Completed
0
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 1 project.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. ME DO RE 2
    Registered status: Active
    97.8% complete

    Al Thanyah Fifth · 407 units, 1 building

    Started
    11 Oct 2020
    Current planned completion
    31 Dec 2025

    9 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.