MERAKI REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 1230Registered with DLD on 12 Mar 2018

On the DLD projects register

Projects
6
Live
4
Completed
2
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
1

No planned completion date has moved since we started checking in Oct 2026, across 6 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4586
    Registered status: Pending
    0% complete

    Madinat Al Mataar · 290 units, 1 building

    Started
    01 Feb 2027
    Current planned completion
    30 Jun 2030
  2. Nirvana Residences - I
    Registered status: Not started
    0% complete

    Me'Aisem First · 326 units, 1 building

    Started
    01 Mar 2026
    Current planned completion
    31 Dec 2028

    9 unit and villa sales in the year to Sep 2026

  3. The Haven III
    Registered status: Active
    6.2% complete

    Wadi Al Safa 3 · 83 units, 1 building

    Started
    01 Aug 2025
    Current planned completion
    31 Dec 2027

    55 unit and villa sales in the year to Sep 2026

  4. The Haven II
    Registered status: Active
    56.3% complete

    Wadi Al Safa 3 · 225 units, 1 building

    Started
    01 Aug 2024
    Current planned completion
    31 Dec 2026

    62 unit and villa sales in the year to Sep 2026

  5. THE HAVEN
    Registered status: Finished

    Wadi Al Safa 3 · 326 units, 2 buildings

    Started
    01 Mar 2023
    Current planned completion
    12 Jul 2025
    Completed
    12 Jul 2025

    102 unit and villa sales in the year to Sep 2026

  6. GENESIS
    Registered status: Finished

    Al Barshaa South Third · 200 units, 1 building

    Started
    25 Sep 2017
    Current planned completion
    25 Feb 2020
    Completed
    25 Feb 2020

    19 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.