Developer
MEYDAN GROUP (L.L.C)
DLD developer number 1181Registered with DLD on 16 Mar 2017
On the DLD projects register
- Projects
- 6
- Live
- 2
- Completed
- 4
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 6 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2Registered status: Active51% complete
Ghadeer Al tair · 228 land plots
- Started
- 20 Nov 2024
- Current planned completion
- 19 Nov 2027
- Mohammed Bin Rashid Al Maktoum City District One West - Phase 1Registered status: Active92.6% complete
Ghadeer Al tair · 467 land plots
- Started
- 01 Dec 2023
- Current planned completion
- Not published
- DLD project 2315Registered status: Finished
Al Wasl · 154 units, 2 buildings
- Started
- 01 Oct 2019
- Current planned completion
- 31 Mar 2024
- Completed
- 31 Mar 2024
- DLD project 2363Registered status: Finished
Al Wasl · 374 units, 5 buildings
- Started
- 01 May 2018
- Current planned completion
- 31 Dec 2024
- Completed
- 31 Dec 2024
- DLD project 2364Registered status: Finished
Al Wasl · 165 units, 2 buildings
- Started
- 01 Apr 2018
- Current planned completion
- 30 Sep 2024
- Completed
- 30 Sep 2024
- DLD project 2333Registered status: Finished
Al Wasl · 105 units, 2 buildings
- Started
- 01 Jan 2018
- Current planned completion
- 30 Jun 2024
- Completed
- 30 Jun 2024
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.