Developer
ORCHID LIVING REAL ESTATE L.L.C
DLD developer number 2401Registered with DLD on 13 Jun 2025
On the DLD projects register
- Projects
- 1
- Live
- 1
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
A planned completion date moved once since we started checking in Oct 2026, on 1 of 1 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 12 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Orchid Residence 1Registered status: Active48.5% complete
Madinat Al Mataar · 44 units, 1 building
- Started
- 08 Jul 2024
- Current planned completion
- 31 Mar 2026
Planned date moved once since we started checking in Oct 2026
Source: DLD projects register, read 12 Nov 2026.