Dubai Land Department records

Developer

ORION REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 1110Registered with DLD on 12 Nov 2015

On the DLD projects register

Projects
2
Live
1
Completed
1
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 2 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. ORION BUILDING
    Registered status: Finished

    Al Barshaa South Third · 196 units, 1 building

    Started
    01 Jan 2016
    Current planned completion
    15 Jul 2022
    Completed
    01 Jun 2022

    10 unit and villa sales in the year to Sep 2026

  2. WEST BAY TOWER
    Registered status: Active
    82.5% complete

    Business Bay · 253 units, 1 building

    Started
    01 Jan 2016
    Current planned completion
    07 Feb 2024

    28 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.