Developer
ORO24 REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 1369Registered with DLD on 07 Sep 2021
On the DLD projects register
- Projects
- 5
- Live
- 4
- Completed
- 1
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 5 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- ALBERO BY ORO24Registered status: Active44.8% complete
Wadi Al Safa 2 · 192 units, 1 building
- Started
- 30 Nov 2023
- Current planned completion
- Not published
4 unit and villa sales in the year to Sep 2026
- KYOTO BY ORO24Registered status: Active17% complete
Al Barshaa South Third · 708 units, 1 building
- Started
- 20 Jun 2023
- Current planned completion
- 20 Sep 2026
11 unit and villa sales in the year to Sep 2026
- ELANO BY ORO24Registered status: Active70% complete
Al Barshaa South Third · 339 units, 1 building
- Started
- 01 Apr 2023
- Current planned completion
- 01 Oct 2025
13 unit and villa sales in the year to Sep 2026
- LEVANTO BY ORO24Registered status: Active66% complete
Al Barsha South Fourth · 579 units, 1 building
- Started
- 08 Dec 2022
- Current planned completion
- 08 Dec 2025
14 unit and villa sales in the year to Sep 2026
- TORINO BY ORO24Registered status: Finished
Al Barshaa South Third · 625 units, 6 buildings
- Started
- 08 Jul 2022
- Current planned completion
- 08 Jul 2024
- Completed
- 15 Oct 2025
115 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.