Developer

P C I REAL ESTATE DEVELOPERS L.L.C

DLD developer number 1397Registered with DLD on 06 Dec 2021

On the DLD projects register

Projects
4
Live
3
Completed
1
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
2

No planned completion date has moved since we started checking in Oct 2026, across 4 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4443
    Registered status: Pending
    0% complete

    Saih Shuaib 2

    Started
    30 Jun 2026
    Current planned completion
    31 Dec 2029
  2. South Lofts by Premier Choice
    Registered status: Not started
    0% complete

    Saih Shuaib 2 · 149 units, 1 building

    Started
    15 Jan 2026
    Current planned completion
    30 Jan 2029

    98 unit and villa sales in the year to Sep 2026

  3. GATEWAY BY PREMIER CHOICE
    Registered status: Active
    68% complete

    Al Barsha South Fourth · 152 units, 1 building

    Started
    01 Aug 2023
    Current planned completion
    Not published

    29 unit and villa sales in the year to Sep 2026

  4. barari views
    Registered status: Finished

    Wadi Al Safa 3 · 26 units, 1 building

    Started
    23 Mar 2022
    Current planned completion
    23 Mar 2024
    Completed
    07 Nov 2025

    7 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.