Projects
5
Live
5
Completed
0
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
1

No planned completion date has moved since we started checking in Oct 2026, across 5 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. PEACE AVENUE BY PEACE HOMES
    Registered status: Active
    3.5% complete

    Jabal Ali Industrial Second · 266 units, 1 building

    Started
    01 Jan 2026
    Current planned completion
    31 Jan 2029

    72 unit and villa sales in the year to Sep 2026

  2. Peace Lagoons II by Peace Homes
    Registered status: Active
    4% complete

    Wadi Al Safa 5 · 831 units, 1 building

    Started
    01 Jan 2025
    Current planned completion
    01 Jan 2029

    299 unit and villa sales in the year to Sep 2026

  3. Peace Lagoons by Peace Homes
    Registered status: Active
    4.2% complete

    Wadi Al Safa 5 · 1,000 units, 1 building

    Started
    30 Sep 2024
    Current planned completion
    30 Sep 2028

    223 unit and villa sales in the year to Sep 2026

  4. Sky Vista by Peace Homes
    Registered status: Active
    61% complete

    Al Barsha South Fourth · 72 units, 1 building

    Started
    15 Jun 2024
    Current planned completion
    Not published

    9 unit and villa sales in the year to Sep 2026

  5. Sky Livings by Peace Homes
    Registered status: Active
    60% complete

    Al Barsha South Fourth · 180 units, 1 building

    Started
    05 Jun 2024
    Current planned completion
    Not published

    16 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.