Developer
PEACE HOMES DEVELOPMENT L.L.C
DLD developer number 1745Registered with DLD on 09 Oct 2023
On the DLD projects register
- Projects
- 5
- Live
- 5
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 5 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- PEACE AVENUE BY PEACE HOMESRegistered status: Active3.5% complete
Jabal Ali Industrial Second · 266 units, 1 building
- Started
- 01 Jan 2026
- Current planned completion
- 31 Jan 2029
72 unit and villa sales in the year to Sep 2026
- Peace Lagoons II by Peace HomesRegistered status: Active4% complete
Wadi Al Safa 5 · 831 units, 1 building
- Started
- 01 Jan 2025
- Current planned completion
- 01 Jan 2029
299 unit and villa sales in the year to Sep 2026
- Peace Lagoons by Peace HomesRegistered status: Active4.2% complete
Wadi Al Safa 5 · 1,000 units, 1 building
- Started
- 30 Sep 2024
- Current planned completion
- 30 Sep 2028
223 unit and villa sales in the year to Sep 2026
- Sky Vista by Peace HomesRegistered status: Active61% complete
Al Barsha South Fourth · 72 units, 1 building
- Started
- 15 Jun 2024
- Current planned completion
- Not published
9 unit and villa sales in the year to Sep 2026
- Sky Livings by Peace HomesRegistered status: Active60% complete
Al Barsha South Fourth · 180 units, 1 building
- Started
- 05 Jun 2024
- Current planned completion
- Not published
16 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.