Developer

PRESCOTT REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 1207Registered with DLD on 16 Aug 2017

On the DLD projects register

Projects
11
Live
6
Completed
5
Cancelled
0
Planned completion in the next 12 months
2
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 11 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. The Caden By Prescott
    Registered status: Not started
    0.5% complete

    Bukadra · 229 units, 1 building

    Started
    15 Nov 2025
    Current planned completion
    15 May 2028

    106 unit and villa sales in the year to Sep 2026

  2. Verano By Prescott
    Registered status: Active
    41.1% complete

    Al Hebiah Second · 269 units, 1 building

    Started
    30 Mar 2025
    Current planned completion
    31 Dec 2026

    33 unit and villa sales in the year to Sep 2026

  3. Legado By Prescott
    Registered status: Active
    23.3% complete

    Al Barsha South Fourth · 343 units, 1 building

    Started
    01 Sep 2024
    Current planned completion
    31 Aug 2027

    35 unit and villa sales in the year to Sep 2026

  4. Fairway Residences By Prescott
    Registered status: Active
    50% complete

    Al Hebiah Fourth · 156 units, 1 building

    Started
    01 Jun 2024
    Current planned completion
    Not published

    9 unit and villa sales in the year to Sep 2026

  5. Serene Gardens 2 by Prescott
    Registered status: Active
    70% complete

    Jabal Ali First · 285 units, 1 building

    Started
    01 Jan 2024
    Current planned completion
    Not published

    15 unit and villa sales in the year to Sep 2026

  6. Serene Gardens by Prescott
    Registered status: Active
    61.7% complete

    Jabal Ali First · 184 units, 1 building

    Started
    15 Sep 2023
    Current planned completion
    Not published

    25 unit and villa sales in the year to Sep 2026

  7. ELEVATE by Prescott
    Registered status: Finished

    Al Barshaa South Third · 223 units, 1 building

    Started
    01 Mar 2023
    Current planned completion
    31 Mar 2025
    Completed
    04 Jun 2026

    48 unit and villa sales in the year to Sep 2026

  8. Prime Gardens
    Registered status: Finished

    Al Barshaa South Third · 139 units, 1 building

    Started
    01 Jun 2022
    Current planned completion
    19 Apr 2024
    Completed
    19 Apr 2024

    16 unit and villa sales in the year to Sep 2026

  9. Prime Townhouses
    Registered status: Finished

    Jabal Ali First · 8 villas, 1 land plot

    Started
    16 Jun 2021
    Current planned completion
    30 Sep 2022
    Completed
    30 Sep 2022
  10. Prime Residency 3
    Registered status: Finished

    Jabal Ali First · 292 units, 1 building

    Started
    01 Jun 2021
    Current planned completion
    06 Dec 2024
    Completed
    06 Dec 2024

    27 unit and villa sales in the year to Sep 2026

  11. Prime Views
    Registered status: Finished

    Nad Al Shiba First · 153 units, 1 building

    Started
    01 Oct 2017
    Current planned completion
    30 Apr 2020
    Completed
    02 Mar 2021

    8 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.