Developer
PRESCOTT REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 1207Registered with DLD on 16 Aug 2017
On the DLD projects register
- Projects
- 11
- Live
- 6
- Completed
- 5
- Cancelled
- 0
- Planned completion in the next 12 months
- 2
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 11 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- The Caden By PrescottRegistered status: Not started0.5% complete
Bukadra · 229 units, 1 building
- Started
- 15 Nov 2025
- Current planned completion
- 15 May 2028
106 unit and villa sales in the year to Sep 2026
- Verano By PrescottRegistered status: Active41.1% complete
Al Hebiah Second · 269 units, 1 building
- Started
- 30 Mar 2025
- Current planned completion
- 31 Dec 2026
33 unit and villa sales in the year to Sep 2026
- Legado By PrescottRegistered status: Active23.3% complete
Al Barsha South Fourth · 343 units, 1 building
- Started
- 01 Sep 2024
- Current planned completion
- 31 Aug 2027
35 unit and villa sales in the year to Sep 2026
- Fairway Residences By PrescottRegistered status: Active50% complete
Al Hebiah Fourth · 156 units, 1 building
- Started
- 01 Jun 2024
- Current planned completion
- Not published
9 unit and villa sales in the year to Sep 2026
- Serene Gardens 2 by PrescottRegistered status: Active70% complete
Jabal Ali First · 285 units, 1 building
- Started
- 01 Jan 2024
- Current planned completion
- Not published
15 unit and villa sales in the year to Sep 2026
- Serene Gardens by PrescottRegistered status: Active61.7% complete
Jabal Ali First · 184 units, 1 building
- Started
- 15 Sep 2023
- Current planned completion
- Not published
25 unit and villa sales in the year to Sep 2026
- ELEVATE by PrescottRegistered status: Finished
Al Barshaa South Third · 223 units, 1 building
- Started
- 01 Mar 2023
- Current planned completion
- 31 Mar 2025
- Completed
- 04 Jun 2026
48 unit and villa sales in the year to Sep 2026
- Prime GardensRegistered status: Finished
Al Barshaa South Third · 139 units, 1 building
- Started
- 01 Jun 2022
- Current planned completion
- 19 Apr 2024
- Completed
- 19 Apr 2024
16 unit and villa sales in the year to Sep 2026
- Prime TownhousesRegistered status: Finished
Jabal Ali First · 8 villas, 1 land plot
- Started
- 16 Jun 2021
- Current planned completion
- 30 Sep 2022
- Completed
- 30 Sep 2022
- Prime Residency 3Registered status: Finished
Jabal Ali First · 292 units, 1 building
- Started
- 01 Jun 2021
- Current planned completion
- 06 Dec 2024
- Completed
- 06 Dec 2024
27 unit and villa sales in the year to Sep 2026
- Prime ViewsRegistered status: Finished
Nad Al Shiba First · 153 units, 1 building
- Started
- 01 Oct 2017
- Current planned completion
- 30 Apr 2020
- Completed
- 02 Mar 2021
8 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.