Developer
REEF REAL ESTATE INVESTMENT CO (L.L.C)
DLD developer number 19Registered with DLD on 26 Aug 2007
On the DLD projects register
- Projects
- 3
- Live
- 0
- Completed
- 3
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 3 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 12 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- REEF TOWERRegistered status: Finished
Al Thanyah Fifth · 121 units, 1 building
- Started
- 05 May 2008
- Current planned completion
- 04 Feb 2009
- Completed
- 04 Feb 2009
12 unit and villa sales in the year to Sep 2026
- MADINA TOWERRegistered status: Finished
Al Thanyah Fifth · 205 units, 1 building
- Started
- 26 Aug 2007
- Current planned completion
- 14 Nov 2007
- Completed
- 14 Nov 2007
10 unit and villa sales in the year to Sep 2026
- CRYSTAL TOWERRegistered status: Finished
Business Bay · 425 units, 3 buildings
- Started
- 20 Apr 2007
- Current planned completion
- 26 Jan 2010
- Completed
- 26 Jan 2010
10 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 12 Nov 2026.