Dubai Land Department records

Developer

REPORTAGE PRIME PROPERTIES L.L.C

DLD developer number 1277Registered with DLD on 17 Jul 2019

On the DLD projects register

Projects
10
Live
9
Completed
1
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 10 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Reportage Hills
    Registered status: Not started
    0.4% complete

    Al Hebiah Fifth · 902 villas, 40 land plots

    Started
    30 Jun 2025
    Current planned completion
    30 Jun 2028

    313 unit and villa sales in the year to Sep 2026

  2. Taormina Village 1
    Registered status: Active
    20.4% complete

    Wadi Al Safa 3 · 530 villas, 32 land plots

    Started
    21 Dec 2024
    Current planned completion
    20 Dec 2027

    145 unit and villa sales in the year to Sep 2026

  3. Verdana Residence 2
    Registered status: Active
    20% complete

    Dubai Investment Park First · 239 units, 1 building

    Started
    01 Oct 2024
    Current planned completion
    30 Apr 2026

    86 unit and villa sales in the year to Sep 2026

  4. Verdana 2
    Registered status: Active
    56% complete

    Dubai Investment Park First · 209 villas

    Started
    31 Dec 2023
    Current planned completion
    Not published

    19 unit and villa sales in the year to Sep 2026

  5. Reportage Village 1
    Registered status: Active
    25% complete

    Wadi Al Safa 7 · 1,752 villas, 30 land plots

    Started
    31 Dec 2023
    Current planned completion
    31 Dec 2027

    274 unit and villa sales in the year to Sep 2026

  6. Bianca
    Registered status: Active
    56.1% complete

    Wadi Al Safa 2 · 653 villas

    Started
    30 Sep 2023
    Current planned completion
    31 Dec 2026

    71 unit and villa sales in the year to Sep 2026

  7. Verdana Residence
    Registered status: Active
    96.1% complete

    Dubai Investment Park First · 224 units, 1 building

    Started
    31 Dec 2022
    Current planned completion
    31 Dec 2025

    35 unit and villa sales in the year to Sep 2026

  8. Verdana (Phase 1)
    Registered status: Active
    94.6% complete

    Dubai Investment Park First · 178 villas

    Started
    01 Jul 2022
    Current planned completion
    31 Dec 2025

    22 unit and villa sales in the year to Sep 2026

  9. Verdana(Phase 2)
    Registered status: Active
    94% complete

    Dubai Investment Park First · 127 villas

    Started
    01 Jul 2022
    Current planned completion
    31 Dec 2025

    12 unit and villa sales in the year to Sep 2026

  10. Alexis Tower
    Registered status: Finished

    Jabal Ali Industrial Second · 378 units, 1 building

    Started
    04 Mar 2019
    Current planned completion
    20 May 2024
    Completed
    20 May 2024

    45 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.