Developer
ROSE HOMES INVESTMENT (L.L.C)
DLD developer number 126Registered with DLD on 18 Oct 2007
On the DLD projects register
- Projects
- 5
- Live
- 2
- Completed
- 3
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 5 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 12 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Al Warsan StarRegistered status: Active7.5% complete
Al Warsan First · 48 units, 1 building
- Started
- 12 Oct 2025
- Current planned completion
- 12 Feb 2027
- SHERENA RESIDENCE 2Registered status: Active82% complete
Wadi Al Safa 3 · 120 units, 1 building
- Started
- 01 Oct 2018
- Current planned completion
- 31 Aug 2022
1 unit or villa sale in the year to Sep 2026
- ROXANA RESIDENCERegistered status: Finished
Al Barsha South Fourth · 255 units, 4 buildings
- Started
- 15 Nov 2015
- Current planned completion
- 28 Jul 2019
- Completed
- 01 Apr 2019
14 unit and villa sales in the year to Sep 2026
- SHERENA RESIDENCERegistered status: Finished
Wadi Al Safa 3 · 300 units, 1 building
- Started
- 15 Sep 2014
- Current planned completion
- 15 Mar 2017
- Completed
- 15 Mar 2017
19 unit and villa sales in the year to Sep 2026
- ONTARIO TOWERRegistered status: Finished
Business Bay · 300 units, 1 building
- Started
- 29 Jul 2007
- Current planned completion
- 23 Aug 2010
- Completed
- 23 Aug 2010
53 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 12 Nov 2026.