Dubai Land Department records

Developer

ROZ REAL ESTATE DEVELOPMENT L.L.C

DLD developer number 2093Registered with DLD on 18 Oct 2024

On the DLD projects register

Projects
3
Live
3
Completed
0
Cancelled
0
Planned completion in the next 12 months
0
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 3 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Rose Gardens 2
    Registered status: Active
    51.5% complete

    Al Barsha South Fourth · 71 units, 1 building

    Started
    11 Feb 2025
    Current planned completion
    30 Aug 2026

    19 unit and villa sales in the year to Sep 2026

  2. Rose Gardens 1
    Registered status: Active
    43.1% complete

    Al Satwa · 166 units, 1 building

    Started
    24 Jan 2025
    Current planned completion
    23 Jul 2026

    24 unit and villa sales in the year to Sep 2026

  3. Rose Gardens 3
    Registered status: Active
    75.8% complete

    Al Barshaa South Third · 49 units, 1 building

    Started
    17 Sep 2024
    Current planned completion
    02 May 2026

    26 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.