Developer
S.P. INTERNATIONAL 1 LIMITED
DLD developer number 70Registered with DLD on 25 Sep 2008
On the DLD projects register
- Projects
- 1
- Live
- 0
- Completed
- 1
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 1 project.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- S.P. RESIDENCERegistered status: Finished
Warsan Fourth · 1 building
- Started
- 17 Jun 2007
- Current planned completion
- 15 Feb 2015
- Completed
- 15 Feb 2015
Source: DLD projects register, read 11 Nov 2026.