Developer
SABA PROPERTIES DMCC
DLD developer number 269Registered with DLD on 07 Jan 2008
On the DLD projects register
- Projects
- 3
- Live
- 0
- Completed
- 3
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 3 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- SABA TOWER 1Registered status: Finished
Al Thanyah Fifth · 188 units, 1 building
- Started
- 20 Jan 2008
- Current planned completion
- 06 Nov 2008
- Completed
- 17 Oct 2006
18 unit and villa sales in the year to Sep 2026
- SABA TOWER 2Registered status: Finished
Al Thanyah Fifth · 377 units, 1 building
- Started
- 20 Jan 2008
- Current planned completion
- 06 Mar 2008
- Completed
- 06 Mar 2008
30 unit and villa sales in the year to Sep 2026
- SABA TOWER 3Registered status: Finished
Al Thanyah Fifth · 361 units, 1 building
- Started
- 20 Jan 2008
- Current planned completion
- 26 Jan 2008
- Completed
- 26 Jan 2008
30 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.