Developer
SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C
DLD developer number 1598Registered with DLD on 25 Apr 2023
On the DLD projects register
- Projects
- 13
- Live
- 13
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 13 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4572Registered status: Pending0% complete
Wadi Al Safa 3
- Started
- 01 Oct 2026
- Current planned completion
- 30 Sep 2030
- Samana Business Park 2Registered status: Active3% complete
Wadi Al Safa 3 · 174 units, 1 building
- Started
- 01 Nov 2025
- Current planned completion
- 31 Oct 2028
4 unit and villa sales in the year to Sep 2026
- Samana Hills South 2Registered status: Active5.3% complete
Saih Shuaib 2 · 140 units, 2 buildings
- Started
- 01 Sep 2025
- Current planned completion
- 31 Aug 2028
85 unit and villa sales in the year to Sep 2026
- Samana Hills South 3Registered status: Active4.6% complete
Saih Shuaib 2 · 147 units, 1 building
- Started
- 01 Sep 2025
- Current planned completion
- 31 Aug 2028
142 unit and villa sales in the year to Sep 2026
- Samana Imperial GardenRegistered status: Active4.2% complete
Al Barshaa South Third · 344 units, 1 building
- Started
- 01 Jul 2025
- Current planned completion
- 31 Dec 2028
307 unit and villa sales in the year to Sep 2026
- Samana ParkvilleRegistered status: Active13.9% complete
Wadi Al Safa 5 · 428 units, 1 building
- Started
- 01 Jun 2025
- Current planned completion
- 30 Sep 2028
171 unit and villa sales in the year to Sep 2026
- Samana Hills SouthRegistered status: Active12.1% complete
Saih Shuaib 2 · 510 units, 2 buildings
- Started
- 01 Jun 2025
- Current planned completion
- 15 May 2028
69 unit and villa sales in the year to Sep 2026
- Samana Business ParkRegistered status: Active12.8% complete
Wadi Al Safa 3 · 103 units, 1 building
- Started
- 01 Jun 2025
- Current planned completion
- 30 Sep 2028
36 unit and villa sales in the year to Sep 2026
- Samana Barari AvenueRegistered status: Active6% complete
Wadi Al Safa 3 · 349 units, 1 building
- Started
- 01 Jun 2025
- Current planned completion
- 31 Oct 2028
133 unit and villa sales in the year to Sep 2026
- Samana Barari LagoonsRegistered status: Active16.5% complete
Wadi Al Safa 3 · 601 units, 1 building
- Started
- 01 Apr 2025
- Current planned completion
- 31 Mar 2028
59 unit and villa sales in the year to Sep 2026
- Samana Lake ViewsRegistered status: Active22.9% complete
Me'Aisem First · 451 units, 1 building
- Started
- 01 Jun 2024
- Current planned completion
- Not published
13 unit and villa sales in the year to Sep 2026
- Samana Lake Views 2Registered status: Active8.9% complete
Me'Aisem First · 548 units, 1 building
- Started
- 01 Jun 2024
- Current planned completion
- Not published
30 unit and villa sales in the year to Sep 2026
1 more project
- SAMANA SKYROSRegistered status: Active71.3% complete
Al Barshaa South Third · 441 units, 1 building
- Started
- 01 Nov 2023
- Current planned completion
- 30 Apr 2026
19 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.