Dubai Land Department records

Developer

SIDO DEVELOPMENT L.L.C

DLD developer number 1758Registered with DLD on 26 Oct 2023

On the DLD projects register

Projects
2
Live
2
Completed
0
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
0

A planned completion date moved once since we started checking in Oct 2026, on 1 of 2 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 3368
    Registered status: Pending
    0% complete

    Wadi Al Safa 3 · 51 units, 1 building

    Started
    16 Oct 2025
    Current planned completion
    01 Apr 2027

    Planned date moved once since we started checking in Oct 2026

  2. WAREF residences by sido development
    Registered status: Active
    81.1% complete

    Al Barsha South Fourth · 228 units, 1 building

    Started
    29 Feb 2024
    Current planned completion
    01 May 2026

    52 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.