Developer
SOL ARENA REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 2059Registered with DLD on 17 Sep 2024
On the DLD projects register
- Projects
- 2
- Live
- 2
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 2 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4055Registered status: Pending0% complete
Palm Deira
- Started
- 20 Aug 2025
- Current planned completion
- 01 Aug 2028
- Garden ArenaRegistered status: Active5.6% complete
Al Barshaa South Third · 17 units, 1 building
- Started
- 18 Dec 2024
- Current planned completion
- 26 Apr 2026
A project without a page on this site is named by its DLD project number.