Developer
TARAF DEVELOPMENT L.L.C
DLD developer number 1549Registered with DLD on 23 Jan 2023
On the DLD projects register
- Projects
- 5
- Live
- 4
- Completed
- 1
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 5 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Karl Lagerfeld Villas By TarafRegistered status: Active10.5% complete
Wadi Al Safa 3 · 51 villas
- Started
- 01 Sep 2024
- Current planned completion
- Not published
10 unit and villa sales in the year to Sep 2026
- Terra Golf CollectionRegistered status: Active20.1% complete
Me'Aisem First · 77 villas, 17 land plots
- Started
- 31 Mar 2024
- Current planned completion
- 31 Dec 2027
22 unit and villa sales in the year to Sep 2026
- Cello ResidencesRegistered status: Active39% complete
Al Barsha South Fourth · 392 units, 2 buildings
- Started
- 01 Feb 2024
- Current planned completion
- Not published
26 unit and villa sales in the year to Sep 2026
- Terrazzo ResidencesRegistered status: Active95.2% complete
Al Barsha South Fourth · 211 units, 2 buildings
- Started
- 01 Nov 2023
- Current planned completion
- 20 May 2026
8 unit and villa sales in the year to Sep 2026
- LUCERegistered status: Finished
Palm Jumeirah · 38 units, 1 building
- Started
- 01 Jul 2023
- Current planned completion
- 31 Dec 2025
- Completed
- 20 Oct 2026
4 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.