Developer
TIGER PROPERTIES
DLD developer number 581Registered with DLD on 16 Mar 2008
On the DLD projects register
- Projects
- 26
- Live
- 8
- Completed
- 18
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 26 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Sky Gate TowerRegistered status: Active4.7% complete
Al Barsha South Fifth · 431 units, 1 building
- Started
- 15 Sep 2025
- Current planned completion
- 29 Feb 2028
217 unit and villa sales in the year to Sep 2026
- AURESTA TOWERRegistered status: Active4.4% complete
Al Barsha South Fourth · 840 units, 1 building
- Started
- 01 May 2025
- Current planned completion
- 31 Dec 2028
327 unit and villa sales in the year to Sep 2026
- ANANDA RESIDENCESRegistered status: Active3.2% complete
Al Hebiah First · 1,027 units, 2 buildings
- Started
- 01 Feb 2025
- Current planned completion
- 31 May 2028
276 unit and villa sales in the year to Sep 2026
- GUZEL TOWERSRegistered status: Active7.3% complete
Al Barsha South Fifth · 522 units, 2 buildings
- Started
- 01 Dec 2024
- Current planned completion
- 25 Dec 2027
156 unit and villa sales in the year to Sep 2026
- Tiger Sky TowerRegistered status: Active10.2% complete
Business Bay · 849 units, 1 building
- Started
- 01 May 2024
- Current planned completion
- Not published
174 unit and villa sales in the year to Sep 2026
- Jade TowerRegistered status: Active11% complete
Wadi Al Safa 3 · 436 units, 1 building
- Started
- 01 Apr 2024
- Current planned completion
- 31 Mar 2027
42 unit and villa sales in the year to Sep 2026
- RED SQUARERegistered status: Active26.7% complete
Al Barsha South Fifth · 835 units, 2 buildings
- Started
- 01 Jan 2024
- Current planned completion
- Not published
107 unit and villa sales in the year to Sep 2026
- VOLGA TOWERRegistered status: Active51.1% complete
Al Barsha South Fifth · 391 units, 1 building
- Started
- 01 Sep 2023
- Current planned completion
- Not published
16 unit and villa sales in the year to Sep 2026
- LILIUM TOWERRegistered status: Finished
Al Barsha South Fifth · 266 units, 1 building
- Started
- 01 Aug 2023
- Current planned completion
- 31 Mar 2026
- Completed
- 01 Oct 2026
11 unit and villa sales in the year to Sep 2026
- ALTAI TOWERRegistered status: Finished
Al Barsha South Fifth · 240 units, 1 building
- Started
- 01 Jun 2023
- Current planned completion
- 31 Jan 2026
- Completed
- 21 Oct 2026
12 unit and villa sales in the year to Sep 2026
- ELBRUS TOWERRegistered status: Finished
Al Barsha South Fifth · 270 units, 1 building
- Started
- 01 Jun 2023
- Current planned completion
- 31 Mar 2026
- Completed
- 03 Sep 2026
21 unit and villa sales in the year to Sep 2026
- NEVA RESIDENCESRegistered status: Finished
Al Barsha South Fourth · 409 units, 1 building
- Started
- 01 Jan 2023
- Current planned completion
- 31 Dec 2025
- Completed
- 12 Mar 2026
70 unit and villa sales in the year to Sep 2026
14 more projects
- Seslia TowerRegistered status: Finished
Al Barsha South Fifth · 378 units, 1 building
- Started
- 01 Dec 2022
- Current planned completion
- 31 Dec 2025
- Completed
- 22 Jul 2026
35 unit and villa sales in the year to Sep 2026
- CLOUD TowerRegistered status: Finished
Al Barsha South Fifth · 456 units, 2 buildings
- Started
- 01 Mar 2022
- Current planned completion
- 28 Feb 2025
- Completed
- 21 Oct 2025
63 unit and villa sales in the year to Sep 2026
- NOBLESRegistered status: Finished
Business Bay · 562 units, 1 building
- Started
- 25 Feb 2020
- Current planned completion
- 31 Aug 2024
- Completed
- 31 Aug 2024
52 unit and villa sales in the year to Sep 2026
- THE V TOWERRegistered status: Finished
Wadi Al Safa 5 · 369 units, 1 building
- Started
- 15 Jan 2020
- Current planned completion
- 05 Sep 2023
- Completed
- 05 Sep 2023
34 unit and villa sales in the year to Sep 2026
- BLUE WAVERegistered status: Finished
Wadi Al Safa 5 · 578 units, 1 building
- Started
- 01 Nov 2019
- Current planned completion
- 30 Jan 2023
- Completed
- 30 Jan 2023
44 unit and villa sales in the year to Sep 2026
- REGINARegistered status: Finished
Al Barsha South Fourth · 328 units, 1 building
- Started
- 24 Jan 2019
- Current planned completion
- 09 May 2022
- Completed
- 23 Mar 2022
15 unit and villa sales in the year to Sep 2026
- THE SQUARERegistered status: Finished
Al Barsha South Fourth · 370 units, 1 building
- Started
- 01 Dec 2017
- Current planned completion
- 31 Dec 2020
- Completed
- 31 Dec 2020
35 unit and villa sales in the year to Sep 2026
- O 2Registered status: Finished
Al Barsha South Fourth · 323 units, 1 building
- Started
- 01 Oct 2017
- Current planned completion
- 30 Jun 2021
- Completed
- 30 Jun 2021
24 unit and villa sales in the year to Sep 2026
- SAMAYARegistered status: Finished
Wadi Al Safa 3 · 212 units, 1 building
- Started
- 16 May 2017
- Current planned completion
- 31 Jul 2019
- Completed
- 31 Jul 2019
- AL JAWHARA TOWERRegistered status: Finished
Al Barsha South Fifth · 532 units, 1 building
- Started
- 31 Aug 2016
- Current planned completion
- 12 Mar 2020
- Completed
- 12 Mar 2020
37 unit and villa sales in the year to Sep 2026
- AL MANARAH TOWERRegistered status: Finished
Al Barsha South Fifth · 259 units, 1 building
- Started
- 15 May 2014
- Current planned completion
- 06 Nov 2017
- Completed
- 06 Nov 2017
21 unit and villa sales in the year to Sep 2026
- DANA TOWERRegistered status: Finished
Al Barsha South Fourth · 154 units, 1 building
- Started
- 15 Jan 2009
- Current planned completion
- 31 Dec 2013
- Completed
- 31 Dec 2013
14 unit and villa sales in the year to Sep 2026
- LAKE CITY TOWERRegistered status: Finished
Al Thanyah Fifth · 443 units, 1 building
- Started
- 15 Jul 2008
- Current planned completion
- 23 Sep 2008
- Completed
- 23 Sep 2008
29 unit and villa sales in the year to Sep 2026
- MARINA PINNACLERegistered status: Finished
Marsa Dubai · 772 units, 1 building
- Started
- 08 May 2005
- Current planned completion
- 19 Jul 2011
- Completed
- 19 Jul 2011
19 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.